PJM Data Center Plan Asks FERC to Cut Hookup Studies From Two Years to One
A PJM data center plan filed with federal regulators on November 16, 2026, would cut the time to study grid hookups for large loads from two years to one, PJM said.
PJM Interconnection operates the grid in 13 states and Washington, D.C., according to TechTarget. The proposal now goes to the Federal Energy Regulatory Commission (FERC) for review and is not an approved rule (PJM Inside Lines).
By the Numbers: The PJM Data Center Filings
- PJM's Fast Energization process would cut projected study timelines for new generation and Large Load transmission service from two years to one (PJM Inside Lines).
- PJM asked FERC for a 60-day comment period and an order within 120 days (PJM Inside Lines).
- A second filing would apply ride-through rules to Large Computational Loads of 50 MW or more, effective January 16, 2027 (PJM Inside Lines).
- On July 22, 2026, nearly 3.9 GW of data centers switched from utility power to onsite generators during a routine grid disturbance (PJM Inside Lines).
- PJM serves about 10 GW of existing Large Computational Load and forecasts additions of up to 30 GW by 2030 (PJM Inside Lines).
What PJM Filed on November 16, 2026
PJM sent two related proposals to FERC on Monday, November 16, 2026. The first sets up a new process called Fast Energization. The second sets operating rules for data centers that are already connected or will be, according to PJM Inside Lines.
PJM said Fast Energization would study new power generation and transmission service for large users, including data centers, in about half the time. It said slow additions of new generation are driving up electricity prices (PJM Inside Lines).
The design has four parts, according to PJM Inside Lines. It studies generation and load together to remove duplicate steps. It moves readiness and financial requirements earlier to weed out speculative power projects and Large Loads.
It also creates new transmission services for data centers and other Large Load customers. Finally, it gives states and utilities clearer information on the cost of serving those customers (PJM Inside Lines).
PJM said that cost information is meant to help determine who pays for system upgrades. It said the change would let states bill Large Loads for transmission costs they drive, as FERC directed (PJM Inside Lines).
How Fast Energization Changes the PJM Interconnection Queue
Interconnection is the study and approval process that lets a power plant or a big customer connect to the grid. PJM said transmission service for Large Loads now runs through different processes. That makes it hard for states to see all the costs that data center growth creates (PJM Inside Lines).
Under the plan, quick screening rounds would give developers early information before they post readiness requirements. PJM said those requirements are now stricter and applied earlier. It said the goal is to limit the queue to projects that are truly ready to build (PJM Inside Lines).
The plan keeps the first-ready, first-served principle of PJM's reformed process. PJM said FERC found that new services should reflect that some Large Loads can limit their grid use. That includes an interim service while network upgrades are built (PJM Inside Lines).
PJM said the filing responds to FERC directives in two parallel dockets on Large Loads and co-located loads. Co-located loads are big users that sit next to a power plant (PJM Inside Lines).
Ride-Through Rules After the July 22 Data Center Event
Ride-through means a facility stays connected during a brief voltage or frequency swing instead of switching to backup power. PJM said the second filing aims to prevent large, sudden load transfers that can strain the grid (PJM Inside Lines).
On July 22, 2026, a 230 kV transmission line in the Dominion zone of Northern Virginia tripped after a mechanical failure. The fault cleared as designed, but data centers still moved to onsite backup generation, according to PJM Inside Lines.
PJM called it the largest load transfer of its kind in its history. It said the event affected voltage, frequency and power flows across the Eastern Interconnection, though its control center managed it safely (PJM Inside Lines).
The filing defines a Large Computational Load as 50 MW or more. New facilities would have to show compliance as a condition of interconnection and operation, according to PJM Inside Lines.
Existing facilities would get one year from the effective date, or one year from commercial operation, whichever is later. PJM called the rules a first step and plans to develop ramp-rate requirements next (PJM Inside Lines).
PJM Data Center Load Forecast: A Morabito Investment Group Analysis
PJM's own numbers show how fast this load class could grow. It serves about 10 GW of Large Computational Load today and forecasts additions of up to 30 GW by 2030 (PJM Inside Lines).
Adding those figures gives up to 40 GW by 2030, or four times today's base, according to a Morabito Investment Group analysis of PJM's November 16, 2026 filing summary. The July 22 transfer of nearly 3.9 GW equals roughly 39% of the current base on the same math.
Timing matters too. If FERC acts within the 120 days PJM requested, an order would arrive by about March 16, 2027, by the same analysis. FERC is not bound by that request.
What the PJM Data Center Proposals Mean for Investors
For data center land and powered shell developers, time to power often decides when a site can earn rent. A powered shell is a building delivered with utility power but without the tenant's computer equipment. A one-year study cycle, if approved, could shorten the carry on land and entitlements in PJM states.
Earlier readiness and financial requirements cut the other way. Developers may need firmer site control and more capital at risk before they know their final grid costs. Clearer cost data for states could also make upgrade costs more visible earlier in underwriting.
Ride-through rules add a design question for owners. In September 2026, Elizabeth Whitney of Meguire Whitney told TechTarget she did not expect major effects on site selection or timelines. She said costs could rise through added equipment or software.
Neil Osnato of Persistence Analytics Group told TechTarget that compliance could involve backup power systems, relays, transfer logic and restart controls. Those comments addressed PJM's September draft, not the final filing.
For more context, see our coverage of FERC's October 2026 ruling on a separate PJM data center curtailment proposal, a different docket. Our report on how much data center power demand utilities have signed and our piece on power availability in data center site selection add background. Related coverage is on our infrastructure sector page.
What to Watch Next
Watch for FERC's comment period, filings from developers, utilities and states, and any order on the 120-day timeline PJM requested. PJM said it will keep working with stakeholders after filing (PJM Inside Lines). Also watch how existing data centers plan to meet the ride-through deadline.
Frequently Asked Questions
What is the PJM interconnection queue?
It is PJM's process for studying power projects and large customers that want to connect to its grid. PJM said current studies for generation and Large Load service are projected to take two years. Its Fast Energization proposal aims to cut that to one year (PJM Inside Lines).
What is the PJM data center load forecast?
PJM said it serves about 10 GW of Large Computational Load today. It forecasts additions of up to 30 GW by 2030 (PJM Inside Lines). PJM defines that category as loads of 50 MW or more.
Has FERC approved the PJM data center proposals?
No. Both proposals were filed on November 16, 2026, and are pending at FERC. PJM asked for a 60-day comment period and an order within 120 days (PJM Inside Lines).
Key Takeaways
- PJM asked FERC on November 16, 2026, to cut Large Load and generation study timelines from two years to one.
- A separate PJM filing would require data centers of 50 MW or more to ride through grid disturbances starting January 16, 2027.
- PJM's figures imply Large Computational Load of up to 40 GW by 2030, four times today's base, per a Morabito Investment Group analysis.
Bottom Line
PJM is trying to move faster on data center hookups while asking developers to commit earlier and operate more predictably. Both proposals still need FERC review. For investors in PJM states, time to power, earlier capital at risk and ride-through equipment are now part of the underwriting.
Image credit: Tonyglen14, via Wikimedia Commons (CC BY 2.0).
Sources
- PJM Inside Lines, PJM Proposal Would Cut Interconnection Process Time in Half, https://insidelines.pjm.com/pjm-proposal-would-cut-interconnection-process-time-in-half/
- PJM Inside Lines, PJM Proposes New Rules To Protect Grid Reliability as Data Center Demand Grows, https://insidelines.pjm.com/pjm-proposes-new-rules-to-protect-grid-reliability-as-data-center-demand-grows/
- PJM Inside Lines, PJM, Dominion Review Large Load Transfer Event, https://insidelines.pjm.com/pjm-dominion-review-large-load-transfer-event/
- TechTarget, PJM proposes ride-through rules for large data center loads, https://www.techtarget.com/it-infrastructure/news/366650189/PJM-proposes-ride-through-rules-for-large-data-center-loads
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.