Data Center Users Lease 50M SF of Industrial Space Through Q3 2026
Data center-related industrial leasing reached 50 million square feet through the third quarter of 2026, up 113% from all of 2025, Cushman & Wakefield reported in research listed on November 20, 2026.
The research, written by Jason Price, head of Americas logistics and industrial research, quantifies data center leasing in warehouses. Tenants include parts makers, logistics firms, and building suppliers.
By the Numbers
- 50 million square feet: data center-related industrial leasing through Q3 2026, up 113% from the full-year 2025 total (Cushman & Wakefield).
- 21%: the rise in total new national industrial leasing over the same comparison (Cushman & Wakefield).
- $659 billion: year-to-date U.S. imports of AI-related equipment, parts, and components, up 62% from a year earlier (Cushman & Wakefield).
- Nearly 11 million square feet: third-party logistics leasing tied to data centers this year, across 10 leases of 500,000 square feet or more (Cushman & Wakefield).
- 47 gigawatts operating and 36 gigawatts under construction: U.S. data center capacity cited in the note (Cushman & Wakefield).
Why data center leasing reaches into warehouses
A data center campus needs a large physical supply chain. Servers, networking gear, power and cooling systems, spare parts, and construction materials all pass through warehouses first. Cushman says that flow is creating a new source of industrial demand in and around data center markets.
Leases of 50,000 square feet or more by tenants that support data center development or operations hit a record in 2026. Their share of national leasing was 2.0% to 2.5% in 2022 and 2023. It roughly doubled to about 5.0% in 2024 and 2025, according to Cushman.
Who is leasing the space
Cushman groups the demand into three tenant types. Third-party logistics providers (3PLs) move critical parts for data center users. Construction suppliers store materials during campus builds, and equipment makers expand distribution near key hubs.
Manufacturers and suppliers of data center parts led year-to-date leasing, followed by construction and building suppliers. Construction and building suppliers made up 30% of year-to-date leasing volume, per Cushman. The author expects much of this demand to last because maintenance and parts replacement continue after a campus opens.
Hyperscalers, the largest cloud companies, signed six new leases of 500,000 square feet or more to store and ship equipment. Those leases cluster in Dallas-Fort Worth, Atlanta, Kansas City, and Charlotte. Long-term contracts between 3PLs DHL and Kuehne + Nagel and hyperscalers also added volume, Cushman says.
Morabito Investment Group analysis of the 2025 base
According to a Morabito Investment Group analysis of Cushman's figures, a 113% rise to 50 million square feet implies a 2025 full-year total of about 23.5 million square feet. That means data center-related users have already added roughly 26.5 million square feet more than all of last year.
Cushman also says Columbus, Phoenix, Atlanta, and Dallas-Fort Worth together produced more than 32 million square feet of this leasing in 2026. If both figures cover the same period, those four markets account for at least 64% of the national total.
Where demand is concentrated
Columbus, Phoenix, Atlanta, and Dallas-Fort Worth each have more than 3,500 megawatts of operating or planned data center capacity, according to Cushman. Data center-related users account for 22% to 41% of year-to-date leasing in Phoenix, Columbus, Kansas City, Virginia, and Dallas-Fort Worth.
Emerging markets are growing faster. Austin-San Antonio, Kansas City, Reno, and West Texas combined are up 274% from last year, and Kansas City leads with 2.2 million square feet. Demand grew more than 300% in Columbus, Northern California, the Carolinas, Kansas City, and Austin-San Antonio compared with 2025.
El Paso, Portland, and Salt Lake City posted notable demand for the first time in 2026. Cushman links that to nearby data center growth.
What it means for industrial investors and developers
Cushman says data center users move early. They often know where campuses will go before construction starts, so they secure space ahead of other tenants. Cushman advises occupiers in major hubs to plan sooner to land well-located Class A buildings.
Developers are responding. Industrial construction pipelines in key data center markets grew over the past year but remain below 2023-2024 peaks. Under-construction space is up 190% in Columbus, 171% in Atlanta, 110% in Nashville, 92% in Phoenix, and 68% in Chicago, year over year.
For investors, Cushman expects advanced manufacturing and data center tenants to lift absorption nationally into 2027. Third-party logistics firms and manufacturers made up more than 55% of leasing over the last two years. The author considers much of the leasing sustainable and says improving fundamentals should support values and net operating income.
Context matters. Data center users help fill space, but they do not remove supply risk in every market. The MIG roundup of new warehouse construction on November 16, 2026 covers recent pipeline activity.
Related data center and manufacturing demand
Data center capital is also flowing into other parts of the market. The MIG report on the Anthropic IPO and data center leasing covers a related data center leasing story. Manufacturing demand is covered in the report on the manufacturing construction boom.
Frequently Asked Questions
How much industrial space are data center users leasing?
Data center-related industrial leasing reached 50 million square feet through Q3 2026, up 113% from the full-year 2025 total, according to Cushman & Wakefield.
Which markets lead data center leasing?
Columbus, Phoenix, Atlanta, and Dallas-Fort Worth lead, with more than 32 million square feet combined in 2026. Kansas City is the leading emerging market at 2.2 million square feet, per Cushman.
Who are the tenants in data center logistics space?
Cushman names third-party logistics firms, construction and building suppliers, and equipment makers. Hyperscalers also signed six leases of 500,000 square feet or more.
Key Takeaways
- Data center-related industrial leasing hit 50 million square feet through Q3 2026, up 113% from all of 2025.
- Four markets, Columbus, Phoenix, Atlanta, and Dallas-Fort Worth, produced more than 32 million square feet of it.
- Cushman expects data center and advanced manufacturing tenants to support absorption into 2027.
Bottom Line
Data centers now pull demand into warehouses as well as power-hungry campuses. The 2026 data from Cushman & Wakefield shows record volume and a clear concentration in a few markets. Investors should check local supply and power plans before treating the trend as nationwide.
Image credit: Photo by Troy Mortier on Unsplash.
Sources
- Cushman & Wakefield, Data Centers: The Newest Logistics Demand Engine
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.