PJM Data Center Curtailment Plan Rejected by FERC as 50 MW Load Registry Wins Approval
The Federal Energy Regulatory Commission rejected PJM's data center curtailment plan on October 9, 2026, but approved a registry for loads of 50 MW or more, according to the FERC order.
The ruling, in docket ER26-3515-000, leaves new data centers in the largest U.S. power grid without a fast lane to connect. Four days later, a federal emergency order let PJM tap backup generators as a last resort.
For investors, the two events point to one lesson. Power certainty, not land, now sets the value of data center sites in the Mid-Atlantic and Midwest.
By the Numbers
- 50 MW: The size at one site that now defines a large load in PJM, approved by FERC on October 9, 2026 (FERC order, ER26-3515-000).
- $325 per MW-day: The price cap at which PJM's 2028/2029 capacity auction cleared in July 2026 (American Public Power Association).
- 6,831 MW: How far that auction fell short of PJM's reliability requirement (American Public Power Association).
- 61,591 MW: Generation PJM expected to be out of service, mostly for fall maintenance, when it sought emergency help (DOE Order No. 202-26-50).
- 67 million: People served by PJM across 13 states and Washington, D.C. (NRDC).
What FERC Rejected in the PJM Data Center Proposal
PJM filed its plan on August 13, 2026 (LandGate). Its core was the Interim Resource Adequacy Service (IRAS).
Under IRAS, new large loads entering service after June 1, 2027 could connect before matching new generation existed. In return, they would accept being curtailed, or cut off, ahead of other customers during grid stress.
A second piece let large loads skip ahead by bringing their own new capacity, known as BYONC. FERC rejected both, plus a rule that would have left these new loads out of the capacity auction's demand curve (FERC order).
FERC said several provisions appear to place obligations directly on new large loads, which are mostly retail customers. It also found that some rules pick which retail customers get cut, and the pay terms appear to set a retail rate (Utility Dive).
Retail rates fall under state authority. FERC also said the framework appears to discriminate against large loads (Microgrid Knowledge).
The order cited "significant discrepancies" between PJM's description of IRAS and its proposed tariff text. It also offered guidance on how PJM could revise and refile the plan (FERC order).
The PJM Data Center Registry FERC Approved
FERC accepted PJM's large-load definition: a peak load of 50 MW or more at one site. Affiliated facilities within one mile count as a single site (FERC order).
It also approved a large-load registry, effective October 12, 2026. Load-serving utilities must report each facility's location, in-service dates, peak load and ramp schedule, backup generation and contracts. PJM will post only combined totals in public.
The order says PJM "must have visibility into all Large Loads in the PJM Region to manage its system and ensure reliability" (FERC order).
PJM must make a compliance filing within 30 days that removes the rejected IRAS and BYONC language (FERC order).
What PJM, Regulators and Analysts Said
Commissioner David Rosner wrote a concurring statement. He said states should set curtailment priorities, and that curtailment should come only after voluntary demand response is used up. "We need state regulators to establish clear rules," he wrote (Bisnow).
Rosner also said that in a grid emergency, non-critical data centers should be shut off before homes, hospitals and schools (Utility Dive). He warned that leaving these loads out of the auction demand curve could signal surplus capacity while the region sheds demand.
PJM spokesman Jeff Shields said PJM is "reviewing the Commission's order with an eye toward how we can fulfill FERC's requirements" (Bisnow). He added that PJM aims to respect state roles and protect existing customers from higher costs or lower reliability (Utility Dive).
Jefferies analysts said the ruling could keep capacity prices higher for longer, which benefits independent power producers such as Constellation Energy, NRG Energy, Talen Energy and Vistra (Utility Dive). They expect future curtailment rules to come from states, with Pennsylvania and Ohio most likely to lead (Bisnow).
The Natural Resources Defense Council took a different view. Claire Lang-Ree, an advocate with its Sustainable FERC Project, said, "At a minimum, PJM's rules must require data centers to bring their own supply." She urged PJM to redraft and refile IRAS (NRDC).
DOE Emergency Order Lets PJM Tap Backup Generation
PJM applied for emergency authority on October 11, 2026, citing unusually warm fall weather and planned outages (American Public Power Association). On October 12, it issued a maximum generation alert for October 13.
Energy Secretary Chris Wright signed Order 202-26-50 under Section 202(c) of the Federal Power Act on October 12, and it runs from October 13 through October 16, 2026 (DOE). PJM had forecast demand near 111,500 MW on October 13 and expected to be within 900 MW of its reserve margin on October 14.
The order lets PJM dispatch listed power plants and direct backup generators, including batteries, to run as a last resort before or during an Energy Emergency Alert 3 (DOE). EEA3 is the top grid emergency level, used when supply can no longer meet demand. Backup units serving hospitals, 911 centers and water plants are excluded.
DOE estimates more than 35 GW of unused backup generation nationwide (Microgrid Knowledge). Bisnow reported the order could require some data centers to switch to on-site backup power. PJM called the step precautionary and said such curtailment is unlikely (Bisnow).
The order says any renewal must be requested before it expires. As of October 16, 2026, no renewal had been posted on the DOE order page we reviewed.
Why PJM Capacity Prices Matter for Data Center Real Estate
PJM's 2028/2029 auction procured 138,318 MW at the $325 per MW-day cap. Cleared supply times price totaled $16.4 billion (American Public Power Association). LandGate notes it was one of the first two auctions in which the whole footprint fell short (LandGate).
According to a Morabito Investment Group analysis of PJM auction results reported by LandGate, the $325 cap equals about $118,625 per MW per year. That is roughly 11 times the $28.92 per MW-day cleared for 2024/2025. On LandGate's example, 300 MW at the cap costs about $35.6 million a year.
Site selectors already rank power near the top of their lists, as we covered in data center site selection and power availability. The FERC ruling adds a new layer: state curtailment policy now bears on where a project can connect and how fast.
Implications for Investors, Owners and Developers
- Power path drives value. Without an interim fast lane, sites with grid headroom or contracted on-site supply may draw stronger interest than raw land with no clear power path.
- The registry adds transparency. PJM will see every 50 MW load, its ramp schedule and its backup generation, which may make speculative projects easier to spot.
- State rules become a site factor. If Pennsylvania and Ohio write curtailment rules, as Jefferies expects, local policy will shape timing and risk.
- Backup generation is an operating asset. The DOE order shows on-site generators can be called on in grid emergencies, which matters to owners and tenants alike.
Capital continues to flow toward power and AI infrastructure, as our data center investment roundup shows. Tenant credit still matters too, as covered in our look at CoreWeave debt and data center landlord risk. More on the asset class is on our infrastructure sector page.
What to Watch
- PJM's 30-day compliance filing and any revised IRAS proposal.
- Curtailment rules from state regulators, especially in Pennsylvania and Ohio.
- Whether DOE issues a new emergency order if fall or winter supply stays tight.
- Aggregated registry data, which could show how much large load is planned and where.
Frequently Asked Questions
What is PJM data center curtailment? It means cutting power to a large load, such as a data center, during grid stress. PJM proposed that new large loads accept curtailment first in exchange for faster connection, and FERC rejected that plan on October 9, 2026 (Utility Dive).
What is the PJM large load registry? It is a database of sites with 50 MW or more of peak load, including location, ramp schedule and backup power. FERC approved it effective October 12, 2026 (FERC order).
Who decides which customers get curtailed first? FERC said that question falls largely to the states, which oversee retail electric service. Commissioner Rosner urged state regulators to set clear rules (Bisnow).
Key Takeaways
- FERC rejected PJM's data center curtailment plan on October 9, 2026, but approved a registry for loads of 50 MW or more.
- A DOE emergency order let PJM tap backup generation from October 13 through October 16, 2026, with 61,591 MW of generation expected offline.
- PJM capacity cleared at $325 per MW-day for 2028/2029, about $118,625 per MW per year, according to a Morabito Investment Group analysis.
Bottom Line
The FERC ruling keeps the question of who gets curtailed with the states, and it leaves PJM to refile. Until new rules arrive, data center value in PJM's footprint will lean heavily on a credible, near-term power path. The registry and state action are the next signals to track.
Image credit: Photo by American Public Power Association on Unsplash.
Sources
- FERC, Order Accepting in Part and Rejecting in Part, PJM Interconnection, Docket ER26-3515-000: https://www.pjm.com/pjmfiles/directory/etariff/FercOrders/9207/20261009-er26-3515-000.pdf
- U.S. Department of Energy, Order No. 202-26-50: https://www.energy.gov/documents/doe-order-no-202-26-50
- Utility Dive, FERC rejects most of PJM's large load interconnection plan: https://www.utilitydive.com/news/ferc-pjm-large-load-interconnection-iras-byonc/832716/
- Bisnow, Federal Regulators Reject Power Cuts to Data Centers That Don't Bring Their Own: https://www.bisnow.com/news/national/data-center-power/federal-regulators-reject-power-cuts-to-data-centers-that-dont-bring-their-own
- LandGate, FERC Rejected PJM's Large Load Plan: https://www.landgate.com/news/ferc-rejected-pjm-s-large-load-plan
- Microgrid Knowledge, Interconnection Crossfire: PJM Grid Constraint Prompts DOE Emergency Order as FERC Rejects 'Bring Your Own Capacity' Proposal: https://microgridknowledge.com/generation/news/55412276/interconnection-crossfire-pjm-grid-constraint-prompts-doe-emergency-order-as-ferc-rejects-bring-your-own-capacity-proposal
- American Public Power Association, DOE Issues Emergency Order Directing PJM to Take Actions to Maintain Grid Reliability: https://www.publicpower.org/periodical/article/doe-issues-emergency-order-directing-pjm-take-actions-maintain-grid-reliability
- American Public Power Association, PJM Capacity Auction Procures 138,318 MW: https://www.publicpower.org/periodical/article/pjm-capacity-auction-procures-138318-mw-generation-resources-capacity-price-comes-cap-325
- NRDC, FERC Rejects PJM's Plan to Protect Electricity Reliability and Consumer Bills from Data Centers: https://www.nrdc.org/press-releases/ferc-rejects-pjms-plan-protect-electricity-reliability-and-consumer-bills-data
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.