Data Center Site Selection: Power Is Now a Top Factor for 79% of Site Selectors
Electric power is now a top site selection factor for 79% of consultants in the Site Selectors Guild's 2026 survey, Bisnow reported on October 13, 2026. The shift reaches well beyond data center site selection. It now shapes factories, refineries and other large industrial projects too.
For investors, the message is simple. Land with a firm path to power is becoming the scarce input. Two decisions in early October 2026, one in Texas and one in Virginia, show how much value now rides on utility timelines and local approvals.
By the Numbers
- 79% of site selection consultants named electric power a top factor in the guild's 2026 survey, with labor availability and geopolitics tied at 50%, according to Bisnow.
- 61% of guild members called utility and infrastructure capacity the No. 1 reason a location gets eliminated, per the guild's own 2026 Pulse Check released in March 2026.
- 31 GW to 66 GW: U.S. data center power demand is projected to rise from 2025 to 2027, according to Goldman Sachs Research.
- 45 projects worth nearly $68 billion were blocked or delayed by local opposition from April to June 2026, according to Data Center Watch.
- Up to 1 GW of data center capacity on about 664 acres won approval in Taylor, Texas, according to Business Wire.
Data Center Site Selection: What the Survey Found
The Site Selectors Guild is a group of 72 consultants who help companies choose where to build. In its 2026 survey, power moved to the top of the list across industries, from advanced manufacturing to aerospace and mineral refining, Bisnow reported. In past years, land, talent and tax incentives led the list.
More than half of the consultants said a lack of power was a leading reason to drop a site, Bisnow reported. Power was not treated as a deal breaker before. About 22% cited community opposition as a top reason to cut a location from a shortlist.
The guild's earlier 2026 Pulse Check pointed the same way. Its survey of 49 members found 76% ranked utility and infrastructure capacity, such as electricity, water and natural gas, as the top factor in location decisions. That report also found 69% rated local opposition as a growing barrier to development.
The full report, The State of Site Selection 2026, was released on September 15, 2026, with Development Counsellors International. Its central theme is that the challenge is now "an increased scarcity of certainty."
What Site Selectors and Developers Said
Land use attorney Ellen Smith, a partner at Parker Poe, said the change is broad. "It's not just data centers. It's industrial. It's everything," she told Bisnow.
Smith said five years ago the first questions were about entitlements and approval timelines. Today, she said, the first question is "Is there power, and can we reasonably get it?"
Barry Broome, CEO of the Greater Sacramento Economic Council, said cost and talent still matter. "It's still cost and talent, but it's now getting weighted so heavily on power," he said. Grady Fitzpatrick of Greater New Orleans Inc. said "the need for power is just off the charts" and that utilities face a large backlog.
Data Center Power Requirements Are Climbing Fast
Goldman Sachs Research projects U.S. data center power demand of 31 gigawatts (GW) in 2025, 41 GW in 2026 and 66 GW in 2027, according to its May 20, 2026 analysis. That is an increase of about 113% in two years. A gigawatt is 1,000 megawatts, roughly the output of a large power plant.
Goldman also projects data centers' share of U.S. peak summer power demand rising from 4.1% in 2025 to 8.5% in 2027. It expects only about 60% of capacity scheduled for the next year to arrive on time after delays and cancellations.
That gap between demand and delivery is what site selectors are pricing. A site that can get power in two years beats a cheaper site that waits five.
Taylor, Texas Approves a 1 GW Campus With Its Own Power
Big Watt Digital and PowerHouse Data Centers announced on October 9, 2026 that Taylor, Texas approved the development agreement for their Taylor Technology Campus, according to Business Wire. The campus is planned for up to 1 GW of hyperscale capacity on about 664 acres in the Austin area.
The campus would run on dedicated, behind-the-meter power. That means generation built on site to serve the campus directly, rather than relying only on the public grid. First power is targeted for the first half of 2028, Connect CRE reported.
The city council voted unanimously to approve the agreement, which lets Taylor annex the site, KUT reported. Council members and staff said annexation gives the city authority to set rules on water use, noise and air quality.
The developers project about $1.3 billion in gross tax revenue for Taylor from 2027 through 2046, per Business Wire. That averages about $65 million a year over the 20 years. They also pledged about $28.2 million in community investments, including $10.2 million for Taylor ISD programs.
Many residents at the meeting urged the council to vote no or to delay, KUT reported. Some said the process moved too fast and asked for more public review. CommercialSearch reported construction is planned for 2027 through 2029.
Loudoun County Tables a Rollback of 15 Data Center Approvals
In Loudoun County, Virginia, the world's largest data center hub, supervisors tabled a proposal on October 6, 2026 to remove existing approvals from 15 projects, Bisnow reported. The projects total about 10.5 million square feet across 30 buildings.
The projects were exempted when the county ended by-right zoning for new data centers in March 2025. By-right zoning lets a project proceed without a separate board vote if it meets the rules.
Supervisors Juli E. Briskman and Laura A. TeKrony sponsored the rollback. They said they were responding to residents who want to limit data center growth, and TeKrony said "we owe it to the community," per Bisnow.
A county staff report estimated the change could expose the county to up to $60 million in liability. Several board members cited that litigation risk. Vice Chair Mike Turner said the county set the rules, businesses relied on them, and the county must live by them.
A land use attorney for one affected owner wrote that the estimate "grossly understates" potential claims, Bisnow reported. The board chair tabled the item, including a proposed audit, for a later date, FOX 5 DC reported.
Implications for Investors, Owners and Developers
Powered land is becoming its own asset class. A parcel with a confirmed utility path, or room for on-site generation, can command a premium over similar land without one. The Taylor campus shows developers are willing to build their own power to avoid grid queues.
Entitlements still matter, but they are less certain than they used to be. The Loudoun debate shows that even approved projects can face review when local priorities change. Investors may want to weigh a community's track record on large projects alongside utility capacity.
The trend also touches infrastructure investment and industrial build-to-suit. Power-heavy manufacturing faces the same constraints, a theme in our look at the manufacturing construction pipeline and build-to-suit demand. Capital is still flowing, as our data center investment roundup showed.
Frequently Asked Questions
What are data center site selection criteria?
Power availability now leads the list, with 79% of guild consultants naming it a top factor, Bisnow reported. Labor, fiber, water, transmission access and local approvals follow. Community acceptance is a growing factor too.
What are data center power requirements?
Large campuses are now planned in gigawatts. The Taylor Technology Campus is planned for up to 1 GW, according to Business Wire. Using Goldman Sachs figures, that one campus equals about 3% of total U.S. data center demand in 2025, according to a Morabito Investment Group analysis.
How many data centers are in Loudoun County?
Loudoun County has more than 250 data centers operating and more than 120 in the pipeline, according to Bisnow. Its eastern edge is known as Data Center Alley.
What to Watch
- Whether Loudoun supervisors bring the tabled rollback or audit back for a vote.
- Progress on the Taylor campus toward first power in the first half of 2028.
- Data Center Watch's next quarterly count of blocked or delayed projects.
- Utility interconnection timelines in major industrial markets.
Key Takeaways
- Electric power is now a top site selection factor for 79% of Site Selectors Guild consultants.
- Goldman Sachs projects U.S. data center power demand rising from 31 GW in 2025 to 66 GW in 2027.
- Utility timelines and local approvals now drive the value of industrial and data center land.
Bottom Line
Data center site selection now starts with one question: can the site get power, and how fast? The answer is setting land values, project timelines and deal risk. Investors in industrial and data center assets are watching utilities and town councils as closely as rents.
Image credit: Photo by Sam LaRussa on Unsplash.
Sources
- Bisnow, Access To Power Now The No. 1 Force Shaping U.S. Site Selection Decisions: https://www.bisnow.com/news/national/economic-development/access-to-power-now-the-no-1-force-shaping-us-site-selection-decisions
- Site Selectors Guild, The State of Site Selection 2026: https://siteselectorsguild.com/research/state-of-site-selection-2026/
- Site Selectors Guild, The 2026 State of Site Selection Pulse Check: https://siteselectorsguild.com/research/pulse-check-2026/
- Site Selectors Guild, 2026 Pulse Check report (PDF): https://siteselectorsguild.com/wp-content/uploads/2026/03/SoSS-2026-PulseCheck_3.20.26.pdf
- Goldman Sachs, US Data Center Power Demand Projected to Double by 2027: https://www.goldmansachs.com/insights/articles/us-data-center-power-demand-projected-to-double-by-2027
- Data Center Watch, Q2 2026 Report: https://www.datacenterwatch.org/q2-2026
- Business Wire, Big Watt Digital and PowerHouse Data Centers Announce Planning Approval for Taylor Technology Campus: https://www.businesswire.com/news/home/20261009368024/en/Co-Development-Partners-Big-Watt-Digital-and-PowerHouse-Data-Centers-Announce-Planning-Approval-for-Taylor-Technology-Campus
- Connect CRE, Developer Duo Greenlit for Taylor Data Center: https://www.connectcre.com/stories/developer-duo-greenlit-for-taylor-data-center/
- CommercialSearch, 1 GW Data Center Project Advances Near Austin: https://www.commercialsearch.com/news/1-gw-data-center-project-advances-near-austin/
- KUT, Taylor City Council Approves Data Center Annexation Agreement: https://www.kut.org/energy-environment/2026-10-09/taylor-tx-annex-data-center-power-plant
- Bisnow, Loudoun County Lawmakers Back Off Stripping 15 Data Center Alley Projects' Approval: https://www.bisnow.com/news/washington-dc/data-center-community-relations/loudoun-county-lawmakers-back-off-stripping-15-data-center-alley-projects-approval
- FOX 5 DC, Loudoun County Leaders Table Debate Over Data Center Approvals: https://www.fox5dc.com/news/loudoun-county-leaders-table-debate-over-data-center-approvals-after-warning-about-potential-litigation-cost
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.