Data Center Power Demand: Utilities Have Signed 120 GW, 22% of Reported Load
Utilities in 53 U.S. service territories have signed about 120 GW of data center load, or 22% of the 537 GW they report, Latitude Media said on November 13, 2026.
The gap matters for anyone tracking data center power demand. Signed load is the part with a signed deal to take service, according to Latitude Media. The rest has not reached that step, and Tech Times said utilities do not count it the same way.
By the Numbers
- 120 GW: signed data center load across 53 utility territories tracked by Latitude Intelligence (Latitude Media, Tech Times).
- 537 GW: total reported data center load in the same territories, about 4.5 times the signed figure (Latitude Media, Tech Times).
- 22 GW: data center load operating today in that footprint, so signed load is about 5.5 times what is online (Latitude Media, Tech Times).
- 12.8 GW of 80.1 GW: Georgia Power's signed load compared with its reported load (Latitude Media, Tech Times).
- 37 GW: new generation that the six largest tracked utilities are soliciting or considering (Latitude Media, Tech Times).
- 33 months: average time from announcement to first power for 14 data centers energized since late 2021 (Latitude Media, Tech Times).
What Latitude Intelligence Found on Data Center Power Demand
Latitude Intelligence is a research platform launched on November 10, 2026, according to Latitude Media and MarketScale. It tracks each utility's data center load by stage: operating, signed and reported, Tech Times said.
Load counts as signed only when a customer has a signed deal to take service, Latitude Media said. That one test lets it compare utilities that report demand in different ways. Some utilities report every inquiry, while others report only signed deals, Tech Times reported.
By that test, the platform counts about 120 GW of signed load and 537 GW of reported load, according to Latitude Media. The November 10 launch post gave rounder figures: about 123 GW under contract out of more than 500 GW, per Latitude Media and MarketScale. We use the later 120 GW figure.
Latitude said the unsigned rest is made up of planning forecasts, letters of interest and press releases, according to Latitude Media. The platform covers more than 700 data center campuses, according to Latitude Media and MarketScale.
Data Center Load Growth Is Running Ahead of the Grid
Signed load is already far larger than what runs today. About 22 GW of data center load runs in the same areas today, so signed load is about 5.5 times what is online, Latitude Media said. The open question, Latitude wrote, is whether new power plants and grid links can keep up.
Some utilities face signed demand far above their own peaks. AEP Ohio has the most signed load of any tracked territory, equal to 235% of its current peak, according to Latitude Media. NIPSCO in Indiana sits at 169% and PPL in Pennsylvania at 145%, according to Latitude Media and Tech Times.
Peak load is the most power a utility's customers use at one time. A signed pipeline above 100% of peak means the data centers under contract would need more power than the whole system now uses at its busiest hour.
Georgia Power Shows the Widest Gap Between Reported and Signed Load
Georgia Power has one of the widest gaps of any utility on the list. Latitude Intelligence counts its signed load at 12.8 GW against 80.1 GW of reported load, according to Latitude Media and Tech Times.
Latitude said it will watch the utility's next large load report, due by the end of November 2026, for changes, Latitude Media said. Georgia Power is also pursuing another 2 to 6 GW of new capacity, the outlet reported.
Utilities Are Soliciting 37 GW of New Generation
On the supply side, the six largest utilities on the platform are seeking or weighing about 37 GW of new power plants, according to Latitude Media and Tech Times. Latitude called this a sign that utilities are starting to plan new supply for that demand.
Dominion is seeking up to 7.3 GW of power it can call on at any time, according to Latitude Media. Final bids are due December 18, 2026, with start dates running through 2036.
AEP has disclosed 4 GW solicitations each for Indiana Michigan Power and Public Service Company of Oklahoma. Xcel has multi-gigawatt procurements underway, the outlet said.
Latitude warned that a request for bids is not a working power plant, just as a signed deal is not a powered data center, according to Latitude Media. Loads that wait for firm service can also wait on line upgrades, and ratepayers could cover part of that bill, depending on how a region splits costs, Latitude Media reported.
Why Timelines and Grid Rules Still Set the Pace
New projects take time to reach power. Across 14 data centers energized since late 2021, the average gap from announcement to first power was 33 months, Latitude Media said. Latitude noted the sample is small, with 19 projects in its data and outliers excluded.
Forecasts can also change fast. In early November 2026, utilities in the PJM grid region sharply reduced their large load forecasts, according to Latitude Media. Jefferies analysts said those cuts could shrink a planned PJM backup power purchase to as little as 630 MW, the outlet reported.
Grid rules are still being written. Five regional grid operators must answer federal regulators' large load orders by November 16, 2026, according to Latitude Media and Tech Times. Southwest Power Pool's answer is due November 20.
Morabito Investment Group Analysis: 417 GW of Reported Load Is Unsigned
About 417 GW of reported data center load has no signed service deal, according to a Morabito Investment Group analysis of figures from Latitude Media. We subtracted the 120 GW of signed load from the 537 GW reported.
By the same method, signed load is 22.3% of reported load. Georgia Power has signed 16.0% of what it reports, or 12.8 GW of 80.1 GW, leaving 67.3 GW unsigned. The 37 GW of open generation solicitations equals about 30.8% of signed load.
What Signed Load Means for Real Estate Investors
For land and powered shell investors, the signed figure is a firmer guide than headline totals. A powered shell is a building with power and core systems ready for a data center tenant to fit out. Sites tied to signed load have a clearer path to power.
Contract terms matter too. Latitude tracks four terms in each large load tariff: the minimum bill, contract length, exit terms and collateral, according to Latitude Media and MarketScale. MarketScale said those terms show how firmly a customer is tied to its request.
Industrial owners near utilities with high signed shares, such as AEP Ohio, NIPSCO and PPL, could see more demand tied to data center building. Signed load is still not a guarantee. Where reported load far exceeds signed load, headline demand deserves more caution.
Frequently Asked Questions
What is the data center power demand forecast?
Forecasts vary because utilities count large loads in different ways. Utilities in 53 territories report 537 GW of data center load, but only about 120 GW is signed, according to Latitude Media. About 22 GW operates today, Latitude Media said.
How fast is data center load growth?
Signed data center load is about 5.5 times what is online in the same areas, according to Latitude Media. At AEP Ohio, signed load equals 235% of the utility's current peak, Tech Times reported.
How long does it take a data center to get power?
The average was 33 months from announcement to first power for 14 projects energized since late 2021, according to Latitude Media. Latitude said the sample is small and excludes outliers.
Key Takeaways
- Utilities have signed about 120 GW of the 537 GW of data center load they report, or 22.3%, according to Latitude Media's November 13, 2026 data.
- Signed data center load is about 5.5 times the 22 GW operating today across the same 53 utility territories.
- Georgia Power has signed 16.0% of its 80.1 GW reported data center pipeline, according to a Morabito Investment Group analysis of Latitude figures.
Bottom Line
Latitude's data shows that most reported data center power demand is not yet under contract. Still, the signed 120 GW is large next to the 22 GW online, according to Latitude Media. For investors, signed load and tariff terms are better guides than headline totals.
For more, see how power drives data center site selection. We also covered the ComEd power guarantee dispute in Joliet and the Fed report on data center debt. Learn more about our infrastructure investment focus.
Image credit: Photo by American Public Power Association on Unsplash.
Sources
- Latitude Media, signed versus reported utility data center load, November 13, 2026: latitudemedia.com
- Latitude Media, "Introducing: Latitude Intelligence," https://www.latitudemedia.com/news/introducing-latitude-intelligence/
- Tech Times, "Latitude Finds Data Center Power Contracts Cover 22% of Reported Load as Utilities Seek Power Plants," https://www.techtimes.com/articles/330794/20261116/latitude-finds-data-center-power-contracts-cover-22-reported-load-utilities-seek-power-plants.htm
- MarketScale, "Latitude Intelligence finds only 123 GW of utilities' data center demand is under contract," https://www.marketscale.com/industries/energy/latitude-intelligence-finds-only-123-gw-of-utilities-data-center-demand-is-under-contract
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.