ComEd Data Center Dispute: $1 Guarantee Offer Puts $20B Joliet Campus on Hold
A ComEd data center dispute has put Hillwood's planned $20 billion Joliet, Illinois campus on hold after the developer offered $1 toward a required power guarantee, The Real Deal reported on November 2, 2026.
The Real Deal's report cites Crain's Chicago Business, which also reported on the clash. The case now sits with a federal court in Chicago, and federal and state regulators have each been drawn in.
By the Numbers
- 2029: when Hillwood says the full letter of credit comes due, once power is set to flow, according to The Real Deal.
- $1: the letter of credit PowerHouse Hillwood posted as initial credit support, according to Utility Dive, citing FERC's decision.
- 1.8 gigawatts and $20 billion: the planned size and cost of the campus, according to Utility Dive.
- 24 two-story buildings and more than 6.9 million square feet: the approved plan, according to The Herald-News.
- 6: other data center developers that signed ComEd agreements and posted the full amount, ComEd's Max Leichtman told Crain's, as reported by The Real Deal.
What Happened in the ComEd Data Center Dispute
In 2025, Commonwealth Edison (ComEd) began requiring new data center developments to post financial guarantees covering the power costs they will need, according to The Real Deal. Hillwood countered the required guarantee for its Joliet project with an offer of $1.
Hillwood argued that the full letter of credit was not due until power begins flowing to the site, some time in 2029, according to The Real Deal. ComEd did not accept that reading and ended the agreement along with the related electricity deal. Hillwood then sued.
The developer is PowerHouse Hillwood Holding, a joint venture of PowerHouse Data Centers and Hillwood, according to Utility Dive. On August 14, 2026, the venture asked the Federal Energy Regulatory Commission (FERC) to reject ComEd's notice of cancellation. The venture said the disagreement concerns the timing of a security deposit.
How FERC Ruled on the Transmission Security Agreement
On September 22, 2026, FERC rejected ComEd's notice canceling the transmission security agreement for the Joliet campus, according to Utility Dive and the FERC order. A transmission security agreement is a contract in which a large power user guarantees its future transmission payments to the utility.
FERC did not decide whether the $1 posting met the contract terms. It declined to take primary jurisdiction, saying the courts can resolve the dispute as well as the agency can, according to Utility Dive. The case is pending in the U.S. District Court for the Northern District of Illinois.
Several commissioners wrote separately. Commissioner David LaCerte said the idea that $1 could provide appropriate security "strikes me as an embarrassing legal fiction," according to Utility Dive. Commissioner David Rosner wrote that "requiring security deposits helps ensure both project viability and transparency."
Chairman Laura Swett and Commissioner Lindsay See wrote that clear, consistent terms for connecting large loads are crucial, according to Utility Dive. They said grid operators and utilities may propose standard cost recovery agreements. Grid operators have until mid-November 2026 to respond to FERC's June show cause orders on large loads.
What the Federal Court Said About the Retail Agreement
A separate track involves the retail electricity agreement. A federal judge denied Hillwood's request to reinstate it, saying jurisdiction lies with the Illinois Commerce Commission (ICC), according to The Real Deal. The ICC is the state agency that regulates utility rates and service.
The same judge called the agreement poorly written, The Real Deal reported. The outlet said that comment could support Hillwood's reading of when the full guarantee is due. The court case remains unresolved.
What Each Side Says
ComEd points to its other customers. "We have six others who signed agreements, and none of them claimed it was ambiguous about what was owed," Leichtman, ComEd's director of economic and workforce development, told Crain's, according to The Real Deal. "They all posted the full amount," he said.
Hillwood says it has a customer lined up for the campus, according to The Real Deal. It has not yet bought the site. In its FERC filing, the venture also argued that Exelon's utilities use agreements that differ from one another rather than standard forms, according to Utility Dive.
The Joliet Technology Center Plan
The Joliet City Council approved an annexation agreement for the project by an 8 to 1 vote on March 19, 2026, according to The Herald-News. The plan calls for four sub-campuses of six buildings each. Construction was set to start in early 2027, with full build-out planned through 2032.
Reported site sizes differ. The Herald-News described 795 acres, The Real Deal reported about 800 acres, and PowerHouse Data Centers lists 755 acres on its project page. PowerHouse also lists power delivery in the fourth quarter of 2028.
This project is separate from the Prologis warehouse park planned on the former Hollywood Casino Joliet site, covered in our November 1 industrial deals roundup.
Why Utility Guarantees Matter to Data Center Investors
ComEd's agreements are 10-year contracts that require data centers to guarantee their transmission rate payments, Leichtman told ABC7 Chicago in March 2026. If a project uses less power than projected, it pays ComEd the difference. That shifts the risk of an unused grid buildout onto the developer.
The campus would cost about $11.1 million per megawatt of planned capacity, according to a Morabito Investment Group analysis of the $20 billion cost and 1.8 gigawatt load reported by Utility Dive. That works out to an average of about 75 megawatts for each of the 24 planned buildings reported by The Herald-News.
For investors, that is collateral that must be posted years before a campus earns rent. Letters of credit tie up bank capacity and carry fees. A guarantee due at signing, rather than at energization, raises the equity a developer needs early in a project.
Implications for Owners, Developers and Land Sellers
Power access is already a top factor in where data centers go, as our coverage of data center site selection and power availability showed. The Joliet case adds a second test: whether a signed utility agreement is fully secured. Sites with funded agreements may command a premium over sites with disputed ones.
Land sellers face timing risk when a buyer's closing depends on a utility contract. Hillwood has not bought the Joliet site, The Real Deal reported. A long court case could delay any purchase.
Local rules also shape these projects, as our data center moratorium tracker shows. Utility collateral is a separate, contract-based hurdle that sits alongside zoning. More on the asset class is on our infrastructure sector page.
What to Watch
- Grid operator responses to FERC's large load show cause orders, due by mid-November 2026, according to Utility Dive.
- Any ruling in the Northern District of Illinois on whether the $1 posting met the contract terms.
- Any filing at the Illinois Commerce Commission on the retail electricity agreement.
Frequently Asked Questions
What is the Joliet data center lawsuit about?
Hillwood sued ComEd after the utility ended its agreements for the planned Joliet campus, according to The Real Deal. The core question is when the full power guarantee is due. Hillwood says the full amount is not due until power flows, and ComEd says other developers paid it in full.
How big is the Joliet data center?
The plan calls for 24 two-story buildings with more than 6.9 million square feet, according to The Herald-News. It would draw 1.8 gigawatts at full use and cost about $20 billion, according to Utility Dive.
What did FERC decide on the ComEd data center agreements?
On September 22, 2026, FERC rejected ComEd's notice canceling the Joliet transmission security agreement, according to Utility Dive. FERC left the credit question to the federal court in Chicago. Two commissioners wrote that security deposits matter for these agreements.
Key Takeaways
- Hillwood offered $1 toward a ComEd power guarantee for its planned $20 billion Joliet data center campus, according to The Real Deal.
- FERC rejected ComEd's cancellation of the transmission agreement on September 22, 2026, but left the credit question to a federal court.
- The campus would cost about $11.1 million per megawatt of planned capacity, according to a Morabito Investment Group analysis of Utility Dive figures.
Bottom Line
The Joliet dispute shows that utility collateral is now a real line item in data center budgets. The court, FERC and the ICC have each taken up part of the case, and none has yet settled when the full guarantee is due. Until then, the campus remains on hold, according to The Real Deal.
Image credit: PowerHouse Data Centers, via PowerHouse Joliet project page (rendering).
Sources
- The Real Deal, $1 offer threatens $20B Joliet data center deal from Hillwood: https://therealdeal.com/chicago/2026/11/02/1-offer-threatens-20b-joliet-data-center-deal-from-hillwood/
- Crain's Chicago Business, data center and Commonwealth Edison dispute (cited by The Real Deal): https://www.chicagobusiness.com/energy/ccb-data-center-commonwealth-edison-battle-20261028/
- Utility Dive, FERC rejects ComEd's cancellation of PowerHouse Hillwood data center contract: https://www.utilitydive.com/news/ferc-exelon-comed-powerhouse-hillwood-data-center/831127/
- Utility Dive, Microsoft, PowerHouse Hillwood dispute data center service agreements: https://www.utilitydive.com/news/microsoft-powerhouse-hillwood-data-center-service-ferc/828566/
- FERC eLibrary, order in the ComEd and PowerHouse Hillwood proceeding, accession 20260922-3114: https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260922-3114&optimized=false
- ABC7 Chicago, ComEd plans to lessen burden of electric costs for consumers concerned about data centers: https://abc7chicago.com/post/comed-plans-lessen-burden-electric-costs-consumers-concerned-data-centers-being-built-northern-illinois/18737823/
- The Herald-News (Shaw Local), Joliet OKs controversial 795-acre data center: https://www.shawlocal.com/the-herald-news/2026/03/19/joliet-oks-795-acre-data-center
- PowerHouse Data Centers, PowerHouse Joliet: https://powerhousedata.com/data-center/powerhouse-joliet
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.