Data Center Moratorium Tracker: Moratoriums Top 11 Restriction Tools in 4,269 Records

Article details
Published:
October 26, 2026
Updated:
Read length:
7
 mins

Local governments cited moratoriums in 4,269 data center meeting documents from October 2025 to September 2026, the most of 11 restriction tools, according to a GatherGov review reported by CRE Daily on October 26, 2026.

The same review found about 2,100 jurisdictions in all 50 states discussed some kind of data center restriction in that window, CRE Daily reported. For anyone using a data center moratorium tracker to screen sites, the bigger finding is that state law, not local mood alone, often decides which tool a town reaches for.

By the Numbers

  • Nearly 99,000 local agendas, minutes and other records mentioning data centers were reviewed, per CRE Daily.
  • Moratoriums appeared in 4,269 documents and bans or prohibited-use rules in 2,307, according to GatherGov.
  • Moratorium mentions rose from 0.4% of data center documents in October 2025 to 8.7% in July 2026, per CRE Daily.
  • Since January 2026, moratorium talk surfaced in 1,030 jurisdictions and reached formal action in 632, according to the GatherGov Data Center Moratorium 2026 Tracker.
  • Of those, 270 jurisdictions adopted a moratorium and 25 extended one, per GatherGov.

What the Data Center Moratorium Tracker Shows

GatherGov, a firm that monitors local government meetings, sorted a year of records into 11 policy tools. Its chart ranks them by the number of documents that discuss each one, as published by GatherGov on October 20, 2026.

  • Moratoriums: 4,269 documents, the most-cited restriction in 37 states.
  • Bans or prohibited-use rules: 2,307 documents.
  • Water-use rules: 724 documents.
  • Noise limits: 479 documents.
  • State legislation: 415 documents.
  • Special or conditional use permits: 362 documents.
  • Curative amendments: 354 documents, 353 of them in Pennsylvania.
  • Size or megawatt caps: 162 documents.
  • Referendums or citizen petitions: 84 documents.
  • Setbacks or buffers: 72 documents.
  • Emergency or interim ordinances: 11 documents.

The ten local tools account for 8,824 document references, according to a Morabito Investment Group analysis of the GatherGov counts. Moratoriums make up 48.4% of that total and bans make up 26.1%. Together, the two account for nearly three of every four references.

One caution applies to that math. A single document can discuss more than one tool, so the total measures references, not separate meetings.

Georgia, California and North Carolina led on moratoriums, with Florida and Wisconsin also active, CRE Daily reported. Bans were the top tool in New Jersey, California, Louisiana, Arkansas, Rhode Island and Virginia.

How Fast Restriction Talk Grew

The moratorium share climbed for most of the year. It peaked at 8.7% of data center documents in July 2026, or nearly one in 11, according to GatherGov. Ban references peaked earlier, at 4.6% in June, and then eased, per CRE Daily.

GatherGov also found that talk of restrictions grew faster than data center discussion overall. In other words, the rise is not just a side effect of more projects reaching local agendas.

State Law Shapes the Tool

The same local goal can take very different legal forms. A developer could face a pause in Georgia, a ban in New Jersey, a curative amendment in Pennsylvania and a water dispute in Texas, CRE Daily noted.

Georgia. Counties can adopt a moratorium by simple resolution, which helps explain why pauses dominate there, according to GatherGov. Georgia also led the tracker with 45 jurisdictions in a formal moratorium process.

Data Center Moratorium Pennsylvania: The Curative Amendment Route

Pennsylvania's Supreme Court struck down a one-year moratorium in Naylor v. Township of Hellam in 2001, GatherGov noted. Towns instead declare their own zoning ordinance defective. That step, a curative amendment, gives them 180 days to fix the gap.

During those 180 days, rival applications are blocked under the state planning code, per CRE Daily. Upper Mount Bethel's solicitor explained the approach at a July 24, 2026 meeting, citing the township's lack of data center rules.

New Jersey. State law bars development moratoriums unless a qualified health official certifies an imminent danger, according to GatherGov, so towns remove data centers from the list of allowed uses. New Jersey logs about 20 restriction documents per 100 data center documents, the highest rate in the country.

The timing rule matters here. Zoning in force when a complete application is filed governs that project, a speaker warned at a September 2, 2026 New Brunswick council meeting, per CRE Daily.

Data Center Moratorium Texas: Water and County Limits

Texas counties have little zoning power, so local debate centers on water, CRE Daily reported. San Angelo adopted water rules in June 2026 that require closed-loop cooling and cap water draw, per GatherGov.

Hill County adopted a moratorium in May 2026 and was sued by developer RCM Hill, LLC for $100 million, The Texas Tribune reported. Commissioners voted unanimously to rescind it and adopt a developer checklist instead.

Cities have more authority. San Marcos voted 4 to 3 on June 16, 2026 to make data centers ineligible in every zoning district, The Texas Tribune reported. It became the first Texas city to ban them.

Other Local Examples

  • Barnes County, North Dakota approved a six-month moratorium on May 19, 2026 after the state's attorney said a year was too long, per CRE Daily.
  • In Conneaut, Ohio, a speaker at a July 13, 2026 council meeting urged conditional use permits instead of a moratorium, according to GatherGov.
  • Monterey Park, California voters passed Measure NDC in June 2026 with 88.34% support, a permanent ban, per GatherGov and Techstrong IT.

The Moratorium Tracker Uses a Different Window

The two GatherGov datasets do not measure the same thing. The restriction review counts documents from October 2025 through September 2026. The moratorium tracker counts jurisdictions from January through early September 2026, per GatherGov.

In the tracker, 120 jurisdictions had a measure formally introduced or at first reading. Another 232 had directed staff study or legal review, and 172 had public requests only. After Georgia's 45 jurisdictions came North Carolina with 39, Florida with 37, Wisconsin with 36 and New Jersey with 33.

Most moratoriums run 6 to 18 months, with 12 months most common, the tracker found. So far, 9 jurisdictions rejected a proposed moratorium in 2026, 5 repealed one and 3 let one expire.

State action matters too. A New York executive order signed July 14, 2026 paused discretionary state environmental permits for data centers of 50 megawatts or more, Foley & Lardner reported. Fast Company described it as a one-year pause and the first of its kind by a state.

Implications for Investors, Owners and Developers

Entitlement risk now varies sharply by state legal regime. Site selection has long weighed power and land, as our post on data center site selection and power availability covered. The GatherGov data suggests a third screen: what tools local governments can legally use.

Land held for future data center use carries timing risk. A 6 to 18 month pause can push back closings, power interconnection milestones and lease start dates. In Pennsylvania, a curative amendment can block rival applications for 180 days.

Where towns prefer conditional use permits, approvals turn into project-by-project hearings. That can add time and conditions, though it keeps a path to approval open. Sites already zoned for the use, with power secured, in places with fewer restrictions may command premiums, though no source here measures that effect.

Local action also sits alongside federal and county policy. See our coverage of the Broward County data center moratorium vote and the Senate permitting reform bill for data centers. More on the asset class is on our infrastructure sector page.

What to Watch

  • Whether moratoriums adopted in 2026 expire, get extended or turn into permanent rules.
  • Court challenges like the Hill County suit, which can test county authority.
  • Further state-level action, which GatherGov counts as its own restriction tool.

Frequently Asked Questions

What is a data center moratorium?

It is a temporary freeze on new data center applications while a local government writes rules. GatherGov's tracker found most run 6 to 18 months, with 12 months most common. A ban, by contrast, removes the use from zoning indefinitely.

Is there a data center moratorium map or tracker?

Yes. GatherGov publishes a Data Center Moratorium 2026 Tracker with a state-by-state status map, last updated October 21, 2026. It counts 632 jurisdictions that reached formal action since January 2026.

Does Pennsylvania allow a data center moratorium?

Pennsylvania courts have blocked moratoriums, according to GatherGov. Towns instead use curative amendments, which give them 180 days to rewrite zoning. GatherGov found 353 of the 354 curative amendment documents came from Pennsylvania.

Key Takeaways

  • Moratoriums appeared in 4,269 local data center documents from October 2025 to September 2026, more than any other restriction tool, according to GatherGov.
  • Moratoriums and bans make up 74.5% of references to the ten local restriction tools, according to a Morabito Investment Group analysis of GatherGov data.
  • State law drives the choice of tool, so data center site screens now need a legal review alongside power and land.

Bottom Line

The GatherGov data shows data center restrictions spreading across all 50 states, but in different legal forms. Moratoriums lead the count, while bans, curative amendments, water rules and permit hearings fill in where state law steers towns. For investors, the result is entitlement risk that has to be read state by state and town by town.

Image credit: GatherGov, via Data Center Moratorium 2026 Tracker.

Sources

Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.