Permitting Reform Bill: Senate Plan Makes 20 MW Data Centers Pay Full Grid Costs
The permitting reform bill filed in the Senate on September 30, 2026 would make data centers of 20 megawatts or more pay the full added grid costs they create, McGuireWoods says.
The bill is the Bipartisan American Affordability and Jobs Act of 2026 (BAAJA). It also sets firm review deadlines and shorter windows for lawsuits. Bisnow reported on October 18, 2026 that the bill is expected to clear the Senate in the lame-duck session after the November midterm elections.
By the Numbers
- 417 pages: the length of the committee agreement, which is not yet final, according to McGuireWoods.
- 20 MW: the size at which data centers fall under the new ratepayer cost rules, per Bisnow.
- 150 days: the proposed deadline to file most court challenges to federal energy and infrastructure approvals, according to McGuireWoods.
- One year and two years: the proposed deadlines for environmental assessments and environmental impact statements, per McGuireWoods.
- One third: the cut in the standard Endangered Species Act review, from 90 days to 60, according to a Morabito Investment Group analysis of the McGuireWoods summary.
- November 9, 2026: the date Congress returns, with a Senate floor vote not expected before then, per McGuireWoods.
What the Permitting Reform Bill Would Do
Four senators introduced the bill on September 30, 2026, according to the Senate Environment and Public Works Committee. They are Shelley Moore Capito, who chairs that committee, and Mike Lee, who chairs the Energy and Natural Resources Committee. The two committees' ranking members, Sheldon Whitehouse and Martin Heinrich, joined them, giving the bill two sponsors from each party.
The release says the bill reflects input from lawmakers of both parties and a range of stakeholders. Bisnow says the bill is being called "the most significant permitting reform bill in years," according to its October 18 report.
The bill would set firm permit deadlines, exempt more projects from lengthy reviews and limit how long approvals can be challenged, Bisnow reported. It would also change parts of three major environmental laws.
Permitting Reform 2026: Changes to NEPA, Water and Species Reviews
The National Environmental Policy Act (NEPA) is the federal law that makes agencies study how the projects they approve or fund affect the environment. Under the bill, NEPA would be treated as a disclosure law that does not require any particular outcome, according to McGuireWoods.
Environmental assessments would face a one-year deadline and full environmental impact statements a two-year deadline. Projects whose only federal tie is a loan or loan guarantee would fall outside NEPA. In most cases, only those who commented during the review could sue.
Under the Clean Water Act, state water-quality certifications for interstate transmission lines and gas pipelines would be capped at nine months, the law firm said. Maximum terms for certain discharge permits and general wetlands permits would double from five years to 10 years.
Standard formal consultations under the Endangered Species Act would drop from 90 days to 60 days. Historic preservation reviews would start and generally end alongside NEPA reviews, according to McGuireWoods.
Protection for Approved Projects
Permitted projects would keep their permits "absent extraordinary circumstances, violations of law, or court order," the EPW release says. The release also says the bill preserves the ability of Tribes to formally consult.
McGuireWoods says the protection covers federal approvals in effect on or after September 16, 2026, for projects with nonfederal sponsors. Remedies for a wrongful revocation could include a court award of 25% to 50% of unrecovered total project costs, paid from the federal Judgment Fund.
Energy projects that need federal permits but no full review would get a one-year decision deadline. Sponsors could enforce it in court. If a court sends an approval back to an agency, the agency would have up to 180 days to act, according to McGuireWoods.
What Data Centers Would Pay
The EPW release says the bill requires data centers "to pay for all of their associated transmission costs." Bisnow reported that large data centers would have to cover grid costs that would not exist without their demand, not only upgrades that serve them alone.
McGuireWoods describes two layers. One would have federal regulators charge computing loads of any size for their share of existing system costs plus new expansion costs. The second applies to data centers of 20 MW or more, including phased projects and sites under common ownership.
Those larger sites would bear the full added cost of generation, storage, transmission and distribution built for them. Utilities would need financial guarantees before they build. Customers that leave early would still owe unpaid costs.
States could also set separate rates or allocate service through a competitive process instead of first come, first served.
How Supporters and Opponents See It
The sponsors focus on speed and cost. Lee said the country is held back by "a permitting system that takes too long and costs too much," according to the EPW release. Heinrich said data centers should pay for the grid upgrades they require, adding, "Our bill puts teeth behind that principle."
The Center for Biological Diversity called the bill a "back-door deal," Bisnow reported. Camden Weber, a policy specialist at the group, said, "This would be a golden ticket for huge AI data centers and tech billionaires." Other environmental groups have been more receptive, especially to provisions that speed up transmission, according to Bisnow.
The data center industry is divided. Harmol Samra, CEO of Host Digital, told Bisnow, "Upfront capex, especially speculative, is a death knell," and added, "This is just going to slow everyone down." Jeff Thramann, CEO of LT350, took the other view: "Speed to certainty is going to help everybody."
Tyler Ochs, a partner at Ice Miller, said smaller developers and newer entrants in states without large-load tariffs could feel the change most. "If the federal legislation gets passed, it may be a whole new world for them," he told Bisnow. For the largest operators, he said, "it's business as usual."
Implications for Investors, Owners and Developers
Entitlement risk is the chance a project gets delayed or blocked before it can be built. Firm review deadlines, shorter challenge windows and stronger permit protection would all reduce that risk for projects with a federal permit. Less time in review can also cut carry costs, such as interest and taxes on land.
The likely beneficiaries include transmission, energy, industrial and data center projects that need federal approvals. For investors in infrastructure and energy assets, a clear timeline makes it easier to plan a deal and its loan.
The cost rules cut the other way for builders of data centers with no tenant yet. Utilities and regulators already ask developers for collateral, financial guarantees and funded load studies that can total millions of dollars, Bisnow reported. Paying for grid costs up front would add to that capital need.
That could favor sponsors with deep pockets and preleased build-to-suit projects, where a tenant signs before work starts. Owners of powered land may see pricing shift as buyers weigh who pays for the grid upgrades. Power is already a top factor in data center site selection.
The bill follows other federal moves on large loads. Federal regulators recently ruled on a PJM data center curtailment plan and load registry. Developers near wetlands are also tracking the federal WOTUS rule proposal.
Permitting Reform Update: What to Watch
- Whether the Senate takes up the bill after Congress returns on November 9, 2026, and whether the House follows.
- Changes to the 20 MW threshold or the cost rules as the text moves toward a final version.
- Later rulemakings and state actions, since many provisions would need them, according to McGuireWoods.
Frequently Asked Questions
What is the permitting reform bill in the Senate?
It is the Bipartisan American Affordability and Jobs Act of 2026, introduced on September 30, 2026 by the chairs and ranking members of two Senate committees. It would speed federal environmental reviews and protect approved projects, according to the EPW release.
When could the permitting reform bill pass the Senate?
Bisnow reported that the bill is expected to clear the Senate in the lame-duck session after the November 2026 midterms. McGuireWoods said a floor vote is not expected before Congress returns on November 9, 2026, and the House would also need to act.
How would permitting reform affect data centers?
Data centers of 20 MW or more would pay the full added grid costs their demand creates, according to McGuireWoods. Faster reviews could also speed new transmission lines that serve them.
Key Takeaways
- The Senate permitting reform bill would set one-year and two-year deadlines for federal environmental reviews.
- Data centers of 20 MW or more would pay the full added grid costs their demand creates.
- Faster permits could lower entitlement risk, while higher upfront grid costs could favor well-capitalized, preleased projects.
Bottom Line
The permitting reform bill pairs faster, more certain federal reviews with new grid costs for large data centers. Supporters say it will speed construction and protect ratepayers, while critics say it weakens environmental review or burdens smaller developers. For investors, the final text and the vote timing after November 9, 2026 are the details to follow.
Image credit: Bisnow/Jon Banister, via Bisnow.
Sources
- Bisnow, "Senate Bill Offers Data Centers A Faster Path To Power, But At A Price": https://www.bisnow.com/news/national/data-center-development/senate-bill-offers-data-centers-a-faster-path-to-power-but-at-a-price
- U.S. Senate Committee on Environment and Public Works, "Capito, Lee, Whitehouse, and Heinrich Introduce Bipartisan American Affordability and Jobs Act of 2026": https://www.epw.senate.gov/public/index.cfm/2026/9/capito-lee-whitehouse-and-heinrich-introduce-bipartisan-american-affordability-and-jobs-act-of-2026
- McGuireWoods, "Bipartisan American Affordability and Jobs Act of 2026 Proposes Sweeping Reform for Energy and Infrastructure Projects": https://www.mcguirewoods.com/client-resources/alerts/2026/10/bipartisan-american-affordability-and-jobs-act-of-2026-proposes-sweeping-reform-for-energy-and-infrastructure-projects/
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.