SpaceX Data Center Arizona: Proposed 747-Acre, 6 GW Campus Heads to Dec. 9 Hearing

Article details
Published:
November 8, 2026
Updated:
Read length:
7
 mins

SpaceX is behind a proposed 747-acre data center campus in Cochise County, Arizona, that would draw about 6 gigawatts at full build-out, under an October 30, 2026 county application. The company confirmed its role at a community meeting on November 4, 2026, as reported by KVOA and 13 News.

The SpaceX data center Arizona plan was filed under the name Tombstone Resources LLC, according to the special use application. Nothing is approved. The Cochise County Planning and Zoning Commission is scheduled to hold a public hearing on December 9, 2026, according to KVOA and the Gila Herald.

By the Numbers

SpaceX Data Center Arizona Proposal: What the Application Says

The site sits along U.S. Highway 191 near the unincorporated community of Cochise. KVOA and the Gila Herald both put it about 13 miles from Willcox (KVOA; Gila Herald). The land is zoned Rural, and the applicant is under contract to buy the cooperative's parcel, per the application.

The campus would be built in four phases. Phase 1 covers buildings totaling about 1,500 megawatts, and initial electric service for construction is targeted for March 2027, according to the application. The plan also includes 24 gigawatt-hours of battery energy storage, which the filing says would keep computers running through grid outages.

Power would come from the grid through Sulphur Springs Valley Electric Cooperative (SSVEC) and Arizona Electric Power Cooperative (AEPCO) to a utility-owned substation on the site. The filing says there would be no on-site power plant apart from the batteries. Natural gas generators of about 10 megawatts per building would serve only critical loads (application).

The applicant also asks for three changes to Rural rules. It wants buildings and outdoor equipment up to 40 feet tall against a 30-foot limit. It also seeks site coverage of up to 50 percent against a 25 percent standard, plus around-the-clock construction (application).

Water Use, Cooling and the Willcox Basin

Water was a top concern at the meeting, according to KVOA and 13 News. The application says the campus would be dry-cooled, using air rather than water, with no cooling towers.

Total operating water use at full build-out would be about 7 to 10 acre-feet a year, about what 20 to 30 Arizona homes use, according to the application. The filing says no new production well is proposed and no groundwater would be pumped for industrial use. Nonpotable needs would come from the power station's treated wastewater or trucked water.

Reporting by the Arizona Republic, published in the Arizona Daily Star, adds a caveat. Experts told the Republic that the water used to generate electricity raises data centers' total water footprint. The permit did not estimate that indirect use.

What SpaceX Says the Campus Would Deliver

SpaceX presented the plan through Riley Trettle, its head of energy and supercomputer department, according to KVOA and the Gila Herald. "We are committed to living and working and being dedicated, energetic community members," Trettle told the crowd, KVOA reported.

Trettle told attendees in breakout sessions that the company intends to hire its permanent staff locally, according to KVOA and the Gila Herald. The application projects about 250 operations staff when the first buildings open, rising to about 1,000 at full build-out.

The filing says the power deal is structured so the campus pays above the cooperatives' cost of service. It projects SSVEC bills falling by about 10 to 40 percent and $13 million to $53 million a year for the SSVEC Foundation (application). Those electricity figures are subject to Arizona Corporation Commission approval, the filing notes.

On taxes, the application says the project is expected to lower the property tax burden on existing taxpayers. It adds that property tax outcomes depend on state law and on decisions reserved to the county and its taxing jurisdictions (application).

Residents' Concerns About the Cochise County Data Center

Residents raised questions about water, electricity demand, noise and wildlife, according to 13 News and the Gila Herald. The Willcox Playa nearby is a wintering area for sandhill cranes, a point the application itself acknowledges.

Some attendees doubted that local residents would fill the promised jobs, KVOA reported. "We don't know enough, therefore just say no," attendee Michael Gregory told 13 News.

Others supported the plan. "We need AI centers. It's the future," attendee Herald Satterlee told 13 News. A retired federal wildlife specialist told the Republic he favored firm permit conditions on water, noise and light (Arizona Daily Star).

Jason Bowling, chief executive of SSVEC, said both the excitement and the concerns are valid. "I think we just need to let the facts come out and let folks evaluate it for themselves," he told 13 News.

The applicant name also drew questions. SpaceX representatives said they used Tombstone Resources LLC because the SpaceX name draws outside attention, according to KVOA and the Gila Herald.

Morabito Investment Group Analysis: Land and Grid Cost per Gigawatt

The application's own figures imply about 125 acres of land per gigawatt of demand (747 acres divided by about 6 gigawatts). That works out to roughly 8 megawatts per acre, according to a Morabito Investment Group analysis of the Tombstone Resources application.

The $3.6 billion grid package equals roughly $600 million per gigawatt, an approximate figure based on the stated 6 gigawatts. The nine buildings would total about 4.4 million square feet. The midpoint of the projected annual property tax range is about $68.5 million.

These are simple ratios of the applicant's projections, not appraised values or approved terms. They are useful mainly as a yardstick for comparing other large campuses as their filings become public.

What a Proposed Multi-Gigawatt Campus Means for Investors

Power-first site selection is the clearest lesson. The proposed campus sits beside an existing generating station, echoing the trend in our coverage of power availability in data center site selection. Google's planned campus, described in our post on the Google Wyoming data center, is another rural, power-led project.

Our earlier post on the Riot Platforms Corsicana AI lease also noted Lambda's planned campus in Lowndes County, Alabama.

Entitlement risk is the second lesson. A gigawatt figure in a filing is a request, not a finished project. This one still needs a zoning decision, and its electricity terms need state utility regulators' approval.

For nearby land, a 5,500-worker construction peak would test local housing, roads and services if the project moves ahead. Investors tracking infrastructure real estate may watch how cooperatives fund grid upgrades and how counties write permit conditions.

What to Watch Before the December 9 Hearing

The hearing is set for 4 p.m. on December 9, 2026, according to KVOA and the Gila Herald. KVOA reported that the commission has the final say on the request unless it is appealed to the Board of Supervisors.

The applicant must also file a summary of the November 4 meeting, including concerns raised, before the hearing agenda is published, per the application. Trettle said construction would begin immediately if the authorization is granted, KVOA reported.

Frequently Asked Questions

Where is the SpaceX data center in Arizona?

The proposed campus is on about 747 acres along U.S. Highway 191 near Cochise, next to the Apache Generating Station, per the application. KVOA and the Gila Herald place it about 13 miles from Willcox. It has not been approved.

How many jobs would the SpaceX data center create?

The application projects about 1,000 permanent jobs at full build-out and about 5,500 construction workers at peak. About 250 staff would work there when the first buildings open (application).

When is the Cochise County data center hearing?

The Planning and Zoning Commission hearing is scheduled for 4 p.m. on December 9, 2026, according to KVOA and the Gila Herald. KVOA reported that the decision can be appealed to the Board of Supervisors.

Key Takeaways

  • SpaceX is behind a proposed 747-acre, 6-gigawatt data center campus in Cochise County, Arizona, filed on October 30, 2026.
  • The application projects 1,000 permanent jobs, $3.6 billion of grid upgrades and $34 million to $103 million of annual property tax revenue.
  • Nothing is approved, and the county's zoning hearing is scheduled for December 9, 2026.

Bottom Line

The proposed Cochise County campus shows how far large AI projects will go to find power and land. The applicant's projected benefits and residents' concerns about water, noise and wildlife will both be tested at the December 9 hearing. Until then, every figure here is a projection in a filing, not an approved plan.

Image credit: U.S. Bureau of Land Management Arizona (public domain), via Wikimedia Commons.

Sources

Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.