Riot Platforms Corsicana Lease Worth $28 Billion as Google Backs TeraWulf AI Leases
Riot Platforms leased its entire Corsicana, Texas campus to an AI lab for 15 years and about $28 billion of contracted revenue, the company said on November 4, 2026.
The Riot Platforms Corsicana deal covers 910 megawatts (MW) of critical IT capacity, the largest lease in Riot's history. The same day, TeraWulf said Google will back financing tied to about $19 billion of Anthropic leases in Kentucky. Lambda was also named the anchor of a $33.1 billion Alabama campus.
By the Numbers: Riot Platforms Corsicana Lease and Same-Day AI Deals
- The Corsicana lease runs 15 years, covers 910 MW on a contiguous 332-acre parcel and carries about $28 billion of total contract value (Riot Platforms).
- Average annual rent is about $1.8 billion, including contractual escalators, and total value rises to about $54 billion if both five-year extensions are exercised (Riot Platforms).
- Riot puts total capital cost at $6 million per IT megawatt, or $5.5 billion overall (Yahoo Finance).
- Riot now has 1,151 MW leased and about $38 billion of contracted data center revenue (Riot Platforms).
- TeraWulf's Google credit support covers debt financing tied to about $19 billion of contracted Anthropic lease commitments at its Hawesville, Kentucky campus (TeraWulf).
- Lambda is committing $33.1 billion to the Project Red Clay campus in Lowndes County, Alabama (WSFA).
How the Riot Platforms Corsicana Powered Land Lease Works
Riot calls the deal a triple-net powered land lease. Riot delivers the land, the power infrastructure and finished "powered pads," and it keeps owning the high and medium voltage equipment that serves them (Riot Platforms).
The tenant buys, installs, owns and runs the modular computing equipment on those pads. It also bears substantially all operating costs, with power billed as a pass-through. Rent is due on the full 910 MW whether or not the tenant uses it, Riot said.
Riot's quarterly report on Form 10-Q gives the rent formula. Base rent is $130 per kilowatt of critical IT capacity per month for each delivered block, rising 3% a year (Riot Form 10-Q). The tenant also pays taxes, insurance and site expenses, the filing says.
Delivery comes in three phases, according to the release. Riot plans 400 MW in September 2027, 200 MW in January 2028 and 310 MW in July 2028. Rent on each phase starts no later than 60 days after its powered pads are delivered.
Why $6 Million per Megawatt Matters
CEO Jason Les said the project "will require about half the capital of a Tier 3 build." A Tier 3 data center is a full facility with redundant power and cooling, built and run by the landlord. Riot also estimates an NOI margin of about 99%, since the tenant carries the operating costs.
The capital split is the key detail for investors. Riot will fund $2 million per IT megawatt for site work and electrical infrastructure from existing liquidity (Yahoo Finance). The other $4 million per megawatt will be repaid to the tenant in phases, after each phase is delivered and paying rent.
Riot expects to fund those payments with non-recourse project debt sized to the contracted rent. If market financing is not available, the 10-Q says Riot will give rent credits instead, plus interest at 12% a year. Riot said it does not currently expect to issue equity to fund its announced projects.
Anthropic Data Center Texas: What Riot's Filings Say About the Tenant
Riot's press release describes the tenant only as "a leading Frontier AI Lab." Its 10-Q, filed with the Securities and Exchange Commission on November 4, 2026, names the counterparty as Anthropic PBC (Riot Form 10-Q). The filing says the lease was signed on October 28, 2026 and took effect on November 4, 2026.
The same filing says this tenant also holds Riot's 191 MW lease at Rockdale, Texas, which runs 20 years. Riot's 1,151 MW total includes that lease and its AMD contract. Les said the combined contracts should produce more than $2 billion of average annual net operating income (NOI) at full deployment.
With AMD's 50 MW, that means the same tenant accounts for about 96% of Riot's 1,151 leased MW, by our math from the 10-Q. Investors in powered land should weigh tenant credit as closely as the land and power itself. Our earlier report on Anthropic's IPO filing and its plan to lease dedicated data centers covers the company's own disclosures.
TeraWulf Google Deal: A Credit Backstop for Leases Signed in July 2026
TeraWulf's $19 billion is not a new lease. TeraWulf signed the 20-year Anthropic lease for about 401 MW at its Justified Data Campus on July 6, 2026 (TeraWulf). The new event on November 4, 2026 is Google's credit support.
The $19 billion is the value of the lease commitments, not Google's exposure. TeraWulf's 8-K says each of three Google agreements takes effect when the final data hall under its lease starts (TeraWulf Form 8-K). The support can end if Anthropic, or a guaranteeing affiliate, holds certain investment-grade ratings for at least three months.
If Anthropic misses rent or becomes insolvent, Google may pay the rent due and take over the lease. In some cases it may instead pay a termination fee and gain the right to buy an equity stake in the TeraWulf subsidiary, the 8-K says. TeraWulf noted that Alphabet's senior unsecured debt is rated AA+ by S&P and Aa2 by Moody's.
TeraWulf also signed a definitive engineering, procurement and construction (EPC) agreement with Fluor for three data center buildings. A guaranteed maximum price is still being set, and phased completions are expected from late 2027 through the second quarter of 2028 (TeraWulf).
Lambda Data Center Lowndes County: A $33.1 Billion Alabama Anchor
Lambda, an AI cloud company, was named on November 4, 2026 as the anchor of Project Red Clay in Lowndes County, Alabama. Both Yellowhammer News and WSFA put the investment at $33.1 billion. They report more than 1,000 construction jobs, 225 permanent jobs and more than $1.6 billion for county schools through 2049.
Construction is expected to start in the first quarter of 2027 and take up to five years, Yellowhammer News reported. Lambda said it will pay the full cost of the power and grid infrastructure needed to serve the site. Alabama Power service is still pending regulatory approval.
The project also faces a legal challenge. WSFA reported that a citizen group, the Alabama Rivers Alliance and others filed a lawsuit against the Lowndes County Commission on November 3, 2026. The suit claims violations of Alabama's open meetings and open records laws in approving a tax abatement package, and it asks a judge to void the votes.
Morabito Investment Group Analysis: $47 Billion of AI Lease Value in Two Announcements
Riot's $28 billion and TeraWulf's $19 billion add up to about $47 billion of AI lease commitments in two November 4, 2026 announcements. That figure comes from a Morabito Investment Group analysis of company releases.
That is not $47 billion of new leasing. TeraWulf's leases date to July 2026, and its new event was Google's backstop.
A straight-line split of $28 billion over 15 years is about $1.87 billion a year. Riot's stated average of about $1.8 billion includes escalators, so the gap reflects Riot's own math and lease timing.
At $130 per kilowatt per month, the first full year of base rent on all 910 MW would be about $1.42 billion, by our math from the 10-Q. With 3% yearly increases, base rent grows each year after that.
Riot's $6 million per megawatt across 910 MW works out to about $5.46 billion, in line with its stated $5.5 billion.
Per megawatt per year, Riot's contract value is about $2.05 million, versus about $2.37 million for TeraWulf's $19 billion over 20 years on 401 MW. TeraWulf is delivering full buildings, while Riot delivers powered land, so the gap is not an apples-to-apples price.
What It Means for Real Estate Investors
Powered land is becoming a real estate product of its own. The landlord sells land, power and entitlements, and the tenant funds most of the building. That shifts construction and operating risk to the tenant, but it ties the landlord's income to a few AI tenants.
Credit enhancement is the other lesson. "Cost of capital is fundamental to infrastructure development," said TeraWulf CFO Patrick Fleury. A highly rated sponsor behind the rent can make project loans cheaper, as our coverage of Meta's $15 billion bond sale and AI data center debt shows from the borrower side.
For land owners near large substations, the deals show what grid access can be worth. Investors can track that demand through our infrastructure sector page and our report on Microsoft's data center leases not yet started.
Frequently Asked Questions
Where is the Riot Platforms Corsicana data center?
The campus is in Corsicana, Texas, on a contiguous 332-acre parcel, according to Riot. The whole campus, 910 MW of critical IT capacity, is now leased. Riot plans to deliver the first 400 MW in September 2027.
What is the TeraWulf Google deal?
Google signed three credit support agreements on November 4, 2026 that back certain Anthropic obligations under TeraWulf's Kentucky leases, according to TeraWulf's 8-K. The leases themselves were signed in July 2026 and are worth about $19 billion. Each backstop takes effect when the final data hall under its lease begins.
Where is the Lambda data center in Lowndes County?
The Project Red Clay site is off Highway 80, a few miles west of the Montgomery airport, WSFA reported. Yellowhammer News said the campus is planned near Highway 80 and Alabama Highway 21. Lambda is committing $33.1 billion to it, according to both outlets.
Key Takeaways
- Riot Platforms leased its whole 910 MW Corsicana campus for 15 years and about $28 billion, with average rent near $1.8 billion a year.
- Google's November 4, 2026 backstop supports financing for TeraWulf's $19 billion of Anthropic leases, which were signed in July 2026.
- Riot and TeraWulf together account for about $47 billion of AI lease value in the two announcements, according to a Morabito Investment Group analysis.
Bottom Line
The Riot Platforms Corsicana lease shows a cheaper way to monetize power: rent the land and grid hookup and let the tenant fund the computers. The TeraWulf deal shows how a strong credit sponsor can unlock project debt. Both returns still rest on a small number of AI tenants.
Image credit: TeraWulf, aerial view of the Justified Data Campus site in Hawesville, Kentucky, via TeraWulf Our Sites.
Sources
- Riot Platforms, Riot Platforms Reports Third Quarter 2026 Financial Results and Strategic Highlights: https://www.riotplatforms.com/riot-platforms-reports-third-quarter-2026-financial-results-and-strategic-highlights/
- U.S. Securities and Exchange Commission, Riot Platforms, Inc. Form 10-Q for the quarter ended September 30, 2026: https://www.sec.gov/Archives/edgar/data/1167419/000110465926122417/riot-20260930x10q.htm
- Yahoo Finance, Riot Platforms Signs $28 Billion AI Data Center Lease as Q3 Revenue Reaches $181.4 Million: https://finance.yahoo.com/technology/ai/articles/riot-platforms-signs-28-billion-153235844.html
- TeraWulf, TeraWulf Secures Google Credit Backstop for Project Financing in Support of $19 Billion Anthropic Lease; Executes Definitive Fluor EPC Agreement: https://investors.terawulf.com/news-events/press-releases/detail/148/terawulf-secures-google-credit-backstop-for-project-financing-in-support-of-19-billion-anthropic-lease-executes-definitive-fluor-epc-agreement
- U.S. Securities and Exchange Commission, TeraWulf Inc. Form 8-K dated November 4, 2026: https://www.sec.gov/Archives/edgar/data/1083301/000162828026069810/wulf-20261104.htm
- TeraWulf, TeraWulf Announces Anthropic Lease at Justified Data Campus and Sale of Majority Interest in Abernathy Joint Venture to Fluidstack: https://investors.terawulf.com/news-events/press-releases/detail/142/terawulf-announces-anthropic-lease-at-justified-data-campus-and-sale-of-majority-interest-in-abernathy-joint-venture-to-fluidstack
- Yellowhammer News, Lambda announces $33.1 billion AI data center in Lowndes County, largest economic development project in county history: https://yellowhammernews.com/lambda-announces-33-1-billion-ai-data-center-in-lowndes-county-largest-economic-development-project-in-county-history/
- WSFA, Anchor company named for Project Red Clay data center in Lowndes County: https://www.wsfa.com/2026/11/04/anchor-company-named-project-red-clay-data-center-lowndes-county/
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.