Kraft Data Center in Sutton, MA: Proposed $16 Billion, 900 MW Campus
A proposed Kraft data center in Sutton, MA would represent more than $16 billion of private investment and draw about 900 megawatts, according to a November 9, 2026 town manager memo.
The memo went to the Sutton Select Board ahead of a packed meeting on November 10, 2026. It says the plan is tentative and that no application has been filed, as reported by CBS News Boston and the Worcester Business Journal.
By the Numbers: Kraft Data Center Sutton MA Proposal
- The proposed campus would have 10 buildings and draw roughly 900 megawatts at full build-out (Worcester Business Journal; CBS News Boston).
- The developer values each building at about $1.675 billion, putting the full campus at roughly $16.75 billion in 2026 dollars (Worcester Business Journal; NBC Boston).
- Town staff estimate about $27.8 million a year in property tax with all 10 buildings in fiscal 2035 (Worcester Business Journal; NBC Boston).
- Sutton's entire fiscal 2027 tax levy is about $32 million (CBS News Boston; Worcester Business Journal).
- All property in Sutton is assessed at about $2.8 billion today (Boston Globe; Worcester Business Journal).
What the Memo Says About the Sutton Data Center Proposal
Town Manager Austin J. Cyganiewicz laid out the plan in a memo to the Select Board dated November 9, 2026, according to the Worcester Business Journal.
"The proposal is tentative," he wrote. "No application has been filed, and important details on power, water, equipment and site impacts are still to come," as quoted by CBS News Boston.
The site sits off Boston Road and Providence Road in Sutton, a town of about 9,700 residents south of Worcester. That is according to the Boston Globe and CBS News Boston.
Under the current plan, the first two buildings would open in 2029. Two more would open each year through 2033, for a total of 10, according to CBS News Boston and the Boston Globe.
NBC Boston reported that each building would be roughly 250,000 square feet, or about 2.5 million square feet at full build-out. The Worcester Business Journal reported that the memo calls it the Unified Parkway Data Center project. None of the five outlets reviewed gave the site's acreage.
Who Is Behind the Proposed Campus
The memo names the Kraft Group and Unified Global Packaging Group as the parties behind the plan, according to the Boston Globe. The Worcester Business Journal said the site lies within Unified Global Packaging Group's property. NBC Boston said the packaging company owns the land.
CBS News Boston printed the name as United Global Packaging Group. The Globe, the Worcester Business Journal, NBC Boston and WCVB all use Unified, so this post does too.
The Worcester Business Journal described the Kraft Group as headed by New England Patriots owner Robert Kraft. CBS News Boston said both companies are affiliated with him.
Why Reports Say $16 Billion or $16.75 Billion
Both figures trace back to the same memo. The memo says the campus would represent more than $16 billion of private investment, by the developer's estimate, according to the Worcester Business Journal.
The developer values each building at about $675 million of real property, of which $600 million is electrical, cooling and generator systems. It adds about $1 billion of computer equipment per building. That puts the first phase at about $3.35 billion and the full campus at roughly $16.75 billion, the Worcester Business Journal reported.
NBC Boston cited the same $16.75 billion figure from the town's preliminary review. CBS News Boston, WCVB and the Globe rounded to $16 billion. This post uses "more than $16 billion" for the headline figure.
Tax Math: What the Project Could Mean for Sutton
"Using deliberately conservative values, staff estimates the first two buildings would pay about $10.4 million a year in property tax once fully assessed in FY2031," the memo says. The quote comes from the Worcester Business Journal. That would rise to about $27.8 million a year with all 10 buildings in fiscal 2035.
"Because the Town raises only what its budget requires, the main effect would be lower tax bills," the memo continues. It projects about $2,300 less for the average single-family home in fiscal 2031 and about $5,800 less in fiscal 2035, according to CBS News Boston and the Worcester Business Journal.
The memo also says the project would close the structural budget gap in the town's multiyear financial plan starting in fiscal 2031. NBC Boston reported that the town projects that gap could grow to about $9.1 million by fiscal 2033 without corrective action.
Morabito Investment Group Analysis: $18.6 Million per Megawatt
The developer's estimate works out to about $18.6 million of planned investment per megawatt. That is according to a Morabito Investment Group analysis of memo figures reported by the Worcester Business Journal and NBC Boston, dividing $16.75 billion by 900 megawatts.
The result is an estimate. About 60% of each building's value is computer equipment rather than real estate.
The same analysis finds that the projected $27.8 million in annual tax equals about 86.9% of Sutton's fiscal 2027 levy of $32 million. The real property alone, about $6.75 billion across 10 buildings, would be about 2.4 times the town's current $2.8 billion assessed value.
Resident and Select Board Concerns
All six residents who spoke during about 15 minutes of public comment opposed the project, the Boston Globe reported. One resident told the meeting, "I would like to see this process stop tonight," according to WCVB.
Residents raised questions about noise, water and electricity use, generators, traffic and costs for town services, NBC Boston reported. CBS News Boston said neighbors also cited public health and home values. Another resident asked CBS whether new transmission lines or substations would be needed in town or nearby.
The Select Board chair said, "I have a very strong dose of skepticism and concern about this project," according to WCVB. The chair also told residents, "This is just the very, very beginning of this," NBC Boston reported. The Globe said the board would not vote right away and planned several public forums.
Power, Water and the Approval Path
Unified Global Packaging Group said it is in talks with ISO New England, the regional grid operator, to secure power. It is also exploring reclaimed water for cooling, the Worcester Business Journal reported. WCVB said details on water use have not been released.
Major transmission lines cross the site, the memo says, as reported by the Worcester Business Journal. They include a 345 kilovolt line from Millbury to West Farnum and a 115 kilovolt line. The preliminary plan shows three substations, including a National Grid substation near Dudley Road.
Sutton's zoning bylaws do not address data centers today. The memo points to two main tools: a community benefits agreement and a zoning bylaw amendment. The bylaw would need a Planning Board hearing and a two-thirds Town Meeting vote, per the Worcester Business Journal and NBC Boston.
At the state level, a September 2026 executive order bars state permits for a data center without local approval and a community benefits agreement, the Worcester Business Journal reported. CBS News Boston said the order also requires new data centers to supply their own energy or pay a fee.
What It Means for Data Center and Industrial Land Investors
The Sutton plan shows how far data center demand is reaching for sites with existing high-voltage lines. Power access, not land, is often the deciding factor, a theme covered in our look at how power availability now drives data center site selection.
The tax math matters as much as the grid. A project that could cover most of a small town's levy gives local officials a reason to negotiate rather than reject. Yet it also raises the stakes of every hearing, as our data center moratorium tracker shows.
For owners of nearby industrial and flex land, a campus of this size would bring substations, contractors and suppliers. None of that is assured until zoning, a benefits agreement and a power deal are in place. A similar pattern of a proposed campus heading into local review is playing out with the proposed SpaceX Starbase data center project in Texas.
What to Watch Next
- Public forums and a town FAQ website, which CBS News Boston said town leaders plan in the coming months.
- A possible Town Meeting vote in the spring, as reported by CBS News Boston.
- An independent technical review, the benefits agreement and the bylaw. The memo says all three would run at once over about six months if the town pursues the plan, per the Worcester Business Journal.
- Any update from ISO New England talks on how the campus would get 900 megawatts.
Frequently Asked Questions
Where is the Sutton data center location?
The proposed campus would sit off Boston Road and Providence Road in Sutton, about 10 miles south of Worcester, according to the Boston Globe. NBC Boston reported that Unified Global Packaging Group owns the property.
Is the Kraft data center in Massachusetts approved?
No. The memo says no application has been filed, and town officials stressed that nothing has been approved, CBS News Boston reported. A zoning change would need a two-thirds Town Meeting vote, per NBC Boston.
How big would the Sutton data center be?
The plan calls for 10 buildings drawing about 900 megawatts, according to the memo. The Boston Globe, citing research firm Cleanview, and WCVB said it would be the fourth-largest data center in the United States.
Key Takeaways
- The proposed Kraft data center in Sutton, MA would represent more than $16 billion of private investment and draw about 900 megawatts, according to the town manager's memo.
- Town staff estimate $27.8 million a year in property tax by fiscal 2035, about 86.9% of Sutton's $32 million fiscal 2027 levy.
- No application has been filed, and a zoning change would require a two-thirds Town Meeting vote.
Bottom Line
The Sutton proposal puts a large tax base and a heavy power load in front of a small town at the same time. For investors, the signal is that New England sites with existing transmission lines are now in play. The outcome still depends on local votes, a benefits agreement and a confirmed power supply.
Image credit: Faolin42, via Wikimedia Commons (CC BY 4.0).
Sources
- CBS News Boston, 900-megawatt data center campus proposed for central Massachusetts, backed by Kraft Group, https://www.cbsnews.com/boston/news/sutton-data-center-campus-kraft/
- Boston Globe, The Kraft Group wants to build a $16 billion data center campus in a small Central Mass. town, https://www.bostonglobe.com/2026/11/10/business/kraft-group-data-centers-sutton-mass/
- NBC Boston, Kraft-backed plan for huge data center prompts pushback in Sutton, https://www.nbcboston.com/news/local/kraft-backed-plan-for-huge-data-center-prompts-pushback-in-sutton/4047462/
- Worcester Business Journal, Kraft Group proposes $16B data center complex in Sutton, https://wbjournal.com/article/kraft-group-proposes-16b-data-center-complex-in-sutton/
- WCVB, 'I speak in staunch opposition': Sutton residents slam $16B Kraft data center plan, https://www.wcvb.com/article/sutton-select-board-to-review-16-billion-data-center-proposal/74384942
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.