Data Center Moratorium Wave: Loudoun and 5 Others Pause Projects on November 17

Article details
Published:
November 18, 2026
Updated:
Read length:
5
 mins

Six local governments in six states paused or moved to pause data center approvals on November 17, 2026, led by a 12-month pause in Loudoun County, Virginia, according to Bisnow and local news reports. The actions came on a single evening. Together they show how fast local resistance is spreading to the busiest data center markets in the country.

The pauses do not stop projects already approved. They do slow the pipeline of new sites, which matters for landowners, developers and investors pricing future data center land.

By the Numbers

  • 12 months: the length of Loudoun County's pause on legislative data center and substation applications, retroactive to September 15, 2026 (Bisnow).
  • 33: legislative data center applications active in Loudoun when the board voted 7 to 1, with one abstention (Bisnow).
  • 12: proposed data center projects under review in San Jose that are now on hold (San José Spotlight).
  • 180 days: Salt Lake City's pause, the maximum Utah law allows (KUTV).
  • 45: pending projects directly held up in Loudoun and San Jose alone, according to a Morabito Investment Group analysis of Bisnow and San José Spotlight figures.

Loudoun County's Data Center Pause

Loudoun is often called the data center capital of the world. The county had about 53 million square feet of data centers in 2025, double the total of five years earlier, Bisnow reported.

Virginia law does not allow a moratorium on a land use, the county attorney had advised. Instead, the board used the 12-month review window that state law sets for legislative applications, according to Loudoun Now. Legislative applications include rezonings and special exceptions that need a board vote.

Site plans and other staff-level reviews can still proceed. Substations needed for grid reliability are exempt, and projects in special tax districts such as the Route 28 district are excluded, Loudoun Now reported.

The county is rewriting its data center standards and location rules. A Loudoun County notice said that work is expected to finish in the summer of 2027. Once the pause ends, backlogged cases will be heard at no more than five per meeting.

Five More Data Center Moratoriums and Pauses

The same night, other governments acted in quick succession.

  • San Jose, California: the city council unanimously paused land use approvals for data centers and other large energy users until new standards take effect. Those standards go to the council on December 8, 2026 (San José Spotlight).
  • Salt Lake City, Utah: the council adopted a temporary ordinance pausing data center development for up to 180 days while it drafts zoning rules (KUTV).
  • Michigan City, Indiana: the council approved a temporary moratorium on permits for future projects. A Google project already under construction is exempt (WSBT).
  • Berea, Kentucky: the city unanimously adopted a one-year moratorium on accepting, processing or approving data center applications (WYMT).
  • Eau Claire County, Wisconsin: a planning committee voted 5 to 0 for a 12-month moratorium. The county board will take it up on December 15, 2026 and January 19, 2027 (WQOW).

What Local Officials and Residents Said

Supporters cited noise, emissions, water and power use, and new transmission lines. In Loudoun, more than 90 minutes of public comment included speakers on both sides of the pause, Loudoun Now reported.

Several officials framed the pauses as time to write rules, not bans. Salt Lake City Councilwoman Victoria Petro said the council is not inherently opposed to data centers, per KUTV. She said the city wants an evidence-based way to regulate the industry.

Legal risk remains. Loudoun County Attorney Leo Rogers confirmed the pause is legal but said there is a "real threat of litigation" from applicants, Bisnow reported.

A Broader Trend in Data Center Regulation

The November 17 votes add to earlier actions. Montgomery County, Maryland, began an 18-month freeze in July, and New York State adopted a yearlong moratorium on large data centers the same month, Bisnow reported.

At least seven more states are weighing similar measures, according to National Conference of State Legislatures data cited by Bisnow. Prince William County, Virginia, shrank its by-right data center map in September.

Implications for Investors, Owners and Developers

Entitled land is becoming scarcer and more valuable. Sites with approved zoning, power and water in hand may command a premium as new approvals slow in top markets.

Projects already vested are largely protected. Salt Lake City's Northpoint proposal already has its zoning, Petro told KUTV. Michigan City exempted the Google project under construction.

For land investors, timing risk rises. A pause can add a year or more to entitlements, which raises carrying costs and can push buyers to markets with clearer rules.

What to Watch Next

Watch San Jose's December 8 vote on data center standards and Eau Claire County's board votes in December and January. In Loudoun, watch for lawsuits from applicants and the release of the county's new standards.

For background, see our data center moratorium tracker, our coverage of Amazon's Loudoun County campus and the Virginia data center tax exemption review.

Frequently Asked Questions

What is a data center moratorium?

It is a temporary halt on accepting or approving data center applications while a government writes new rules. Berea, Kentucky's one-year moratorium stops the city from accepting, processing or approving applications and permits, WYMT reported.

Is there a data center moratorium in Virginia?

Virginia does not allow a moratorium on a land use, Bisnow reported. Loudoun County instead paused action on legislative applications for up to 12 months, the review period state law allows.

Do data center moratoriums affect projects already approved?

Generally not. Michigan City exempted a Google project under construction, per WSBT, and Loudoun's pause does not cover staff-level site plan reviews.

Key Takeaways

  • Six local governments in six states paused or advanced data center pauses on November 17, 2026.
  • Loudoun County's 12-month pause covers 33 active legislative applications in the world's largest data center market.
  • Approved and vested data center sites may gain value as new approvals slow.

Bottom Line

Local data center pauses are no longer isolated cases. When the largest market and fast-growing cities act on the same night, investors should treat entitlement risk as a core part of data center underwriting.

Image credit: Loudoun County Board of Supervisors meeting broadcast, via Bisnow, Loudoun Supervisors Halt New Data Center Approvals For Up To One Year.

Sources

Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.