Amazon has withdrawn its data center plan for the 120-acre former George Washington University campus in Ashburn, which it bought for $427 million, Loudoun County Chair Phyllis Randall announced on October 20, 2026. The site will be rezoned for mixed use with data centers barred, according to Bisnow. Amazon will also give the county 25 acres valued at $65 million.

The story of the Amazon data center in Loudoun County shows how entitlement risk can change land value, even in the largest data center market in the world.

By the Numbers

  • Amazon Data Services paid $427 million for the roughly 120-acre Virginia Science and Technology Campus in February 2026, according to Loudoun Now.
  • The withdrawn plan proposed four two-story data center buildings totaling more than 800,000 square feet, according to Fortune.
  • Amazon will dedicate about 25 acres along Route 7 with a fair market value of about $65 million, according to Fortune.
  • Amazon will contribute $5 million to the county's affordable housing trust fund, according to Fortune.
  • Data centers generated about $1.2 billion in property tax revenue in fiscal 2026, equal to 39% of the county budget, according to Fortune.

What Happened With the Amazon Data Center in Loudoun County

Randall announced the agreement at a Board of Supervisors meeting on October 20, 2026, according to Loudoun Now. She said she had been talking with Amazon executives for several weeks. The county and Amazon call the deal "Project Potomac Promise."

Amazon will withdraw its data center site plan and drop any legal action to develop data centers on the site, according to Fortune. The county will fast-track a rezoning application for mixed use on the rest of the land. Housing, both market-rate and attainable, is planned as the main use, according to Bisnow.

Randall said the new zoning district will not allow data centers, even by special exception, according to The GW Hatchet. The 25 dedicated acres are planned for a community arts center and an indoor sports facility. Randall said a fast-tracked rezoning could take up to a year, according to Loudoun Now.

How the Campus Sale and Site Plan Unfolded

George Washington University announced the sale of its Virginia campus in February 2026 without naming the buyer or the price, according to Fortune. In March, The GW Hatchet identified Amazon Data Services as the buyer at $427 million. The Hatchet put the price at roughly $3.5 million per acre.

In late July, Amazon filed a site plan called "Bridgefield Tech Center," according to Fortune. In April, Supervisor Juli Briskman, whose Algonkian District includes the campus, had said the price was about four times the assessed value. She said that price and the zoning made data center construction a reasonable expectation.

By July 2026, Briskman said she strongly opposed the project and would fight it, according to Fortune. She said the site offered chances for education, research, housing and economic development.

Residents started a petition for a moratorium on data center construction, citing natural resource use, traffic, noise and pollution, according to The GW Hatchet. Earlier in October, Loudoun Zoning Administrator Teresa Miller said Amazon needed additional county approval because data centers are not a permitted primary use on the property.

What Each Side Said

"My goal was to disallow data centers or infrastructure that could support data centers on this property," Randall said, according to Fortune. She said she chose to work with Amazon because she saw no reason to go to court if it could be avoided, according to Loudoun Now.

Josh Weissman, the Amazon Web Services vice president for data center capacity delivery, said Amazon views the site's legal development potential differently than the county does, according to Bisnow. He said the company concluded "the best outcome for all is to come together on a shared vision for this campus."

Weissman also said, "There was not a moment where it was decided that this was a bad idea," according to Fortune.

Weissman said that in hindsight Amazon probably would not have bought the campus, according to Loudoun Now. A university spokesperson said the new plans do not affect GW or the sale, according to The GW Hatchet. GW can keep operating on the site for up to about five years while it relocates programs.

Loudoun County Data Center Market Context

Loudoun County reports about 233 data center buildings totaling roughly 56.5 million square feet, according to Fortune. The GW Hatchet put the built total at 54 million square feet, so published figures differ. As of July 2026, Northern Virginia had 266 operating data centers, 23 under construction and 99 planned, according to The GW Hatchet.

The county's rules are also changing. Last year the board ended by-right data center zoning, so new projects now need a special exception, according to Bisnow. The board is moving toward a one-year pause on data center approvals, with a final vote expected in November 2026.

Amazon says it has invested more than $63 billion in Loudoun County since 2011 and employs more than 3,400 people there, according to Fortune. Other counties are weighing similar steps, including the vote covered in our post on the Broward County data center moratorium.

What the Deal Means in Dollars

The dedicated land's stated $65 million value equals about 15.2% of Amazon's $427 million price. That figure comes from a Morabito Investment Group analysis of numbers reported by Fortune and Loudoun Now. Adding the $5 million housing contribution brings Amazon's community commitments to $70 million, or about 16.4% of the price.

The 25 acres are about 21% of the roughly 120-acre site, and their stated value works out to about $2.6 million per acre. That compares with roughly $3.56 million per acre paid for the full campus ($427 million divided by about 120 acres), a gap of about 27%. Acreage figures are approximate, and the parcels may differ in quality.

Implications for Investors, Owners and Developers

Land priced for data center use carries a premium that depends on approvals. Briskman's comment that the price was about four times assessed value shows how much of a sale price can rest on expected zoning. When the expected use is removed, the land is valued on what the new zoning allows.

For land investors, zoning history and local rule changes can matter as much as power and fiber. Loudoun's shift from by-right zoning to special exceptions, and a possible pause, add time and uncertainty to approvals. Power access remains a top site factor, as our post on data center site selection and power availability explains.

Federal policy is also in motion. Our post on the Senate permitting reform bill for data centers covers a plan on grid costs for large loads. For more on how MIG views energy and digital assets, see our infrastructure sector page.

Frequently Asked Questions

Where is the Amazon data center in Loudoun County, VA, that was withdrawn? The withdrawn plan covered the former George Washington University Virginia Science and Technology Campus in Ashburn, according to Bisnow. Amazon bought the roughly 120-acre site for $427 million in February 2026.

How many data centers are in Loudoun County? The county reports about 233 data center buildings totaling roughly 56.5 million square feet, according to Fortune. The GW Hatchet reported 54 million square feet built.

What are Amazon's data center locations in Virginia? Amazon has operated in Northern Virginia's "data center alley" since launching its cloud region there in 2006, according to Fortune. In 2023 it announced plans to invest another $35 billion in Virginia data center campuses by 2040.

What to Watch

  • The rezoning application for the remaining land and its housing mix, which Randall said could take up to a year.
  • The Loudoun board's final vote on a one-year data center pause, expected in November 2026.
  • Town halls and design sessions on the arts center and indoor sports facility.

Key Takeaways

  • Amazon withdrew its plan for more than 800,000 square feet of data centers on a $427 million Ashburn campus, Loudoun County announced on October 20, 2026.
  • Amazon's $65 million land dedication equals about 15.2% of its purchase price, according to a Morabito Investment Group analysis.
  • The case shows that land priced for data center use depends on approvals, even in Loudoun County.

Bottom Line

Amazon and Loudoun County reached an agreement that removes data centers from the former GW campus and shifts it toward housing and community uses. Each side described the deal as an alternative to litigation. For investors, it is a clear example of how entitlement risk can reshape the value of land bought for a specific use.

Image credit: Tony Webster via Wikimedia Commons, AWS facility in Houston, as published by Bisnow.

Sources

Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.

Read more articles