Walla Walla Data Center: Amazon Proposes 3 Buildings on 134 Acres

Article details
Published:
November 9, 2026
Updated:
Read length:
7
 mins

Amazon's proposed Walla Walla data center campus would place three buildings of about 220,000 square feet each on 134 acres, according to a Walla Walla County notice dated September 12, 2026.

The project is under review, and nothing has been approved; the county will make its decision only after an environmental review and a second public comment period, with no timeline set, the Walla Walla Union-Bulletin reported on October 31, 2026.

By the Numbers

What Amazon Has Proposed at Wallula Gap

The proposed Amazon Attalia Data Center Campus sits along Sundance Road, between Dodd and Worden roads. That is about 1.4 miles east of U.S. Highway 12, according to the county project page. The site is part of the Port of Walla Walla's Wallula Gap Business Park.

Beyond the three data halls, the plan includes storage tanks, a 1,400-square-foot security building and a 9,675-square-foot industrial water facility. Site work covers ponds, septic systems, roads, parking and a pad for a substation. A future utility would build that substation, the county said.

The environmental checklist Amazon filed puts total data center floor area at 658,510 square feet. It says construction would be phased over three years, according to the SEPA checklist. Columbia Rural Electric Association would supply power, with backup diesel generators for outages.

The checklist does not state how much electricity the campus would draw, and a widely reported 300-megawatt capacity figure does not appear in the county's posted review documents, so this article does not use it.

Port of Walla Walla Amazon Data Center Land Sale

Port commissioners voted on February 12, 2026, to amend the sale of about 553.96 acres to Amazon Data Services, Inc. The motion passed unanimously, according to the port minutes. The deed was dated March 19, 2026, and the port kept the existing water rights tied to the land, the recorded deed shows.

The price was fixed at $65,000 per acre, for a total of $36,007,400, Elkhorn Media Group reported. The Union-Bulletin put the total at about $36 million. The port also agreed to fund new entrances, an access road and a water line.

How the Plan Compares With the Earlier $4.8 Billion Concept

The current proposal is far smaller than the first plan for the site. In October 2024, the port considered selling 500 acres to a buyer named Advance Phase LLC. That buyer planned a $4.8 billion cluster of 16 data centers, according to Elkhorn Media Group and the Tri-City Herald.

The $4.8 billion figure was not an Amazon estimate; the Tri-City Herald said it came from the port commission's meeting agenda. Amazon Data Services later bought the land as successor to Advance Phase, Elkhorn Media Group reported. Amazon has not given an investment total for the current plan.

Residents' Concerns and Amazon's Stated Plans

Residents are pressing for answers about electricity costs, water use and neighborhood effects, GeekWire reported on November 4, 2026. Of 706 submissions in the comment period that closed on October 12, 2026, only 23 supported the project. That finding came from a Union-Bulletin analysis cited by GeekWire.

More than 500 submissions came from outside Walla Walla County, and many asked for a full Environmental Impact Statement, a deeper study than the county now requires, GeekWire reported. Some local supporters tied their backing to firm limits on water use, lighting and noise, the Union-Bulletin found.

Amazon, for its part, says the campus would create 120 to 150 full-time jobs and that it will pay all of its property taxes rather than seek tax incentives, according to GeekWire. It says it will work with utilities so its data centers do not raise local electricity bills, GeekWire reported.

"We're committed to growing responsibly," an Amazon spokesperson told GeekWire. The company has pointed to its Built Together program, which commits more than $1 billion over five years to communities that host its data centers.

Water, Cooling and the Columbia River

Amazon says the campus would use outside air for cooling about 93% of the year. On the hottest days, it would cool air by passing it through water-soaked pads, according to the Amazon FAQ. The site lies about 0.4 miles from the Columbia River, the checklist states.

The two filings give different cooling water figures. The checklist estimates about 18 million gallons a year at peak, plus about 6 million gallons of groundwater for domestic use. Amazon's FAQ puts annual cooling use at 14 million gallons.

Groundwater from the port would serve as a temporary supply for about a year, after which the campus would switch to Columbia River water under rights now used for seasonal irrigation, according to the SEPA checklist.

Morabito Investment Group Analysis: Land Cost per Building Foot

At the reported $65,000 per acre, the 134-acre campus parcel equals about $8.7 million of land. Spread over the 658,510 square feet of proposed data center space, that is about $13 of land per building square foot. That is according to a Morabito Investment Group analysis of the county's SEPA checklist and Elkhorn Media Group's price report.

The same analysis shows a floor area ratio of about 0.11, meaning the buildings would cover roughly 11% of the parcel's land area in floor space. The campus uses about 24% of the 554 acres Amazon bought. The three buildings are about 19% of the 16 data centers in the 2024 concept.

What the Walla Walla Data Center Review Means for Investors

Data center use is allowed outright in the site's industrial zoning, according to a 2018 county code interpretation. That means the permit decision rests with the Community Development Director, not a public hearing, the county said. The open question is the SEPA threshold determination.

A determination of significance would require a full Environmental Impact Statement and could add time, the county explains. A determination of non-significance, or a mitigated one with conditions, would allow the permit to move ahead. For investors, that step is the main timing risk on this kind of rural, power-rich site.

The deal also gives a public data point for industrial land prices in eastern Washington. Port land sold at $65,000 per acre to a hyperscale buyer, with the port keeping water rights and funding road and water work. Our earlier coverage tracks big tech data center capital spending plans for 2026.

Plans can change even after land closes, as Amazon's withdrawn Virginia proposal showed; see our post on the Amazon data center plan withdrawn in Loudoun County. Water use remains a sector-wide issue, as shown in our report on data center water usage in water-stressed areas. More context is on our industrial sector page.

Frequently Asked Questions

Is the Walla Walla data center an Amazon project?

Yes. Amazon Data Services owns the land and filed the application, according to the county. The project remains proposed and under review.

What did the Port of Walla Walla sell for the Amazon data center?

The port approved the sale of about 554 acres at the Wallula Gap Business Park on February 12, 2026, according to its minutes. The price was about $36 million, Elkhorn Media Group and the Union-Bulletin reported.

Is this Amazon's first data center in Washington state?

It would be among Amazon's first large-scale data center campuses in the state, GeekWire reported. Amazon already runs smaller data centers there, including in Seattle. It has also confirmed a second campus in West Richland.

Key Takeaways

  • Amazon's proposed Walla Walla data center would have three buildings of about 220,000 square feet each on 134 acres.
  • The county has made no decision, and a second comment period will follow its SEPA threshold determination.
  • The land cost about $13 per proposed building square foot, according to a Morabito Investment Group analysis.

Bottom Line

Amazon's Wallula Gap plan is much smaller than the $4.8 billion concept first tied to the site. It is still a proposal, and residents and Amazon have set out sharply different views in the record. The county's environmental finding will shape both the timeline and the conditions that come with any approval.

Image credit: Williamborg, via Wikimedia Commons (CC BY-SA 3.0).

Sources

Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.