HSBC Sells $300M of Data Center Debt at a Discount as Lenders Retreat

Article details
Published:
November 20, 2026
Updated:
Read length:
5
 mins

HSBC sold about $300 million of data center debt tied to the $18 billion Project Jupiter campus in New Mexico at a steep discount, according to reports published on November 17, 2026. The sale is a sign that some lenders are cutting exposure to large AI construction loans.

By the Numbers

  • HSBC sold roughly $300 million of the loan for less than 90 cents on the dollar, per Bisnow.
  • Bloomberg, as republished by The Star, said the price was in the mid-80s.
  • The loan is part of an $18 billion financing from about 20 banks for a campus that could reach 2.45 gigawatts.
  • ING is reportedly seeking buyers for $25 million of the same debt, per Bisnow.
  • Credit default swaps on data center debt have reached an all-time high, and some project bond yields have climbed into double digits (Bisnow).

What Happened in the HSBC Data Center Debt Sale

Bloomberg reported that HSBC sold its share of the construction loan several weeks before the news broke. The sale came shortly after Oracle sent the developer a force majeure notice in September 2026, according to The Star. Force majeure is a contract clause that can excuse or delay obligations when extraordinary events occur.

Bloomberg reported in late September that Oracle used the notice to postpone payments in case the venture collapsed. HSBC declined to comment, and Oracle did not immediately respond to Bloomberg's request.

The financing was marketed to lenders as Project Miner. It was split into tranches tied to different buildings on the campus. Bisnow says the debt closed last year during a boom in lending to AI campuses built for large technology companies.

About Project Jupiter

Project Jupiter is a 1,400-acre campus in Doña Ana County, New Mexico. Stack Infrastructure, backed by Blue Owl, is developing it for OpenAI, Oracle and SoftBank's Stargate initiative, per Bisnow.

The project faces community opposition and regulatory hurdles. Air and pipeline permits have been delayed, according to both reports. Our earlier coverage of Blue Owl's Gainesville, Virginia data center purchase shows how active the same investor has been in this sector.

How the Discount Works: A Simple Calculation

A price of 85 means a buyer pays 85 cents for each dollar of loan principal. On $300 million, that is about $255 million, or roughly $45 million below par, according to a Morabito Investment Group calculation. At 90 cents, the gap would be $30 million.

Add ING's $25 million, and the debt reported for sale reaches $325 million. That is about 1.8% of the $18 billion package, based on a Morabito Investment Group calculation of the figures in these reports. The share is small, but the pricing signal matters more than the size.

Syndicated construction loans can usually be sold. Banks often keep them until a sell-down agreement expires, The Star reports. Banks that exit early often accept a discount larger than the upfront fees they earned.

Why Lenders Are Rethinking Data Center Risk

Bisnow lists several worries: community opposition, tighter regulation, the future of AI cloud providers and the pace of spending by large technology firms. Analysts also point to concentration risk, because so much capital is tied to a few companies pursuing similar plans.

The Star adds that regulatory pushback returned after the November midterm elections and that Nvidia CEO Jensen Huang's sudden departure raised questions about AI growth. For related reading, see our report on the Federal Reserve's financial stability report and data center debt and our story on ING's data center loan sales.

Local limits are also spreading. We tracked one example in Loudoun County's pause on new data center projects.

Implications for Investors, Owners and Developers

For lenders, a discounted sale sets a reference price for similar loans. Other banks may mark their holdings against it. That can tighten credit for new projects.

For developers, higher borrowing costs and stricter lender conditions can delay construction starts. Projects with signed tenants, secured power and approved permits are likely to fare better than projects missing any of those three.

For investors in data center real estate and credit funds, the main questions are tenant credit, power availability and permit timing. Diversifying across tenants and markets reduces the concentration risk analysts describe.

What to Watch

  • Whether other banks sell their Project Jupiter loan shares and at what prices.
  • Whether permits for air and pipeline needs are granted on schedule.
  • Whether Oracle's force majeure notice leads to changed payment terms.
  • Whether yields on data center bonds keep climbing in double digits.

Frequently Asked Questions

What is data center financing?

It is the debt and equity used to build and own data centers. Banks lend during construction, and the loans are later refinanced or sold. The Project Jupiter package totals $18 billion, per The Star.

Why are lenders selling data center loans?

Reports point to project delays, local opposition, permit hurdles and concern about AI spending. Bisnow says lenders worry about concentration risk and the capital needs of the AI boom.

Is data center financing risky?

Risk varies by project. Credit default swaps on data center debt have hit a record high, per Bisnow, which suggests investors see higher risk than a year ago.

Key Takeaways

  • HSBC sold about $300 million of Project Jupiter debt at a price below 90 cents on the dollar.
  • The reported sales, $300 million plus ING's $25 million, equal about 1.8% of the $18 billion package.
  • Permit delays, local opposition and Oracle's force majeure notice are the stated pressure points.

Bottom Line

One discounted loan sale does not mean the data center boom is ending. It does show that lenders now price delay and permit risk more carefully. Investors should look at tenant strength, power access and approvals before treating all AI campuses alike.

Image credit: Photo by Kevin Ache on Unsplash.

Sources

Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.