SoftBank Data Center Ohio Project Tied to $3.7B Charge in $7B Q2 Loss

Article details
Published:
November 10, 2026
Updated:
Read length:
6
 mins

SoftBank Group posted a ¥1.12 trillion ($7.0 billion) Q2 net loss on November 10, 2026, after a $3.7 billion charge on data center power equipment, including for its Ohio campus, its financial report shows.

The SoftBank data center Ohio project named in the filing is the PORTS-Pike Technology Campus in Pike County. It was SoftBank's first net loss in almost two years, according to Bloomberg as published by The Japan Times.

By the Numbers

  • ¥1,115.3 billion: Net loss attributable to owners for the July to September 2026 quarter, or about $7.0 billion, per SoftBank's Q2 FY2026 data sheet.
  • ¥597.2 billion ($3.73 billion): Loss on power generation equipment for U.S. AI data center projects, per the SoftBank financial report.
  • $9.5 billion: Advance payments made for the PORTS-Pike power project and others from fiscal 2025 through September 30, 2026, per the SoftBank earnings presentation.
  • ¥129 billion: The quarterly profit analysts had expected on average, according to Bloomberg via The Japan Times.
  • ¥461.9 billion: Second quarter finance cost, up from ¥174.7 billion a year earlier, per the SoftBank data sheet.
  • 15.9%: Loan to value ratio at September 30, 2026, below the company's 25% ceiling for normal times, per the SoftBank investor briefing.

What the SoftBank Data Center Ohio Charge Covers

The charge sits in Silver Bands 7, a subsidiary funded by SoftBank Group and its second Vision Fund. It signed capacity reservations and equipment contracts to secure power generation gear for U.S. AI data centers, the financial report says.

Those projects include the PORTS-Pike Technology Campus in Pike County, Ohio. Silver Bands 7 had paid ¥1.50 trillion ($9.48 billion) for this procurement through September 30, 2026, according to SoftBank.

The unit then revised its equipment plan to match the needs of current and planned projects. SoftBank booked ¥457.0 billion ($2.85 billion) for advance payments that cannot be refunded and ¥140.2 billion ($0.88 billion) for contract changes and settlements, the report shows.

In return, Silver Bands 7 may receive rebates of up to $2.1 billion over 10 years on future equipment purchases, subject to conditions. SoftBank did not record those rebates as an asset because the amount could not yet be determined, per the filing.

SoftBank also booked a separate ¥72.5 billion impairment on buildings it bought in Lordstown, Ohio, to make data center equipment, according to the financial report. That loss is not part of the $3.7 billion charge.

Where the Ohio Campus Stands

SoftBank lists PORTS-Pike at 8.0 gigawatts of IT capacity, with OpenAI as the tenant under a 20-year contract. As of September 30, 2026, the campus was "preparing for construction," according to the earnings presentation.

NVIDIA is providing credit support on land, power and shell buildings for the first 4.25 gigawatts, the presentation adds. SB Energy, the SoftBank developer, has said capacity should come online in phases beginning in 2028, per its August 17, 2026 press release.

SoftBank said it made these payments in advance because it expected shortages of power equipment. It still expects to recoup the investment through project financing, according to the earnings presentation. After the loss, $6.6 billion of the advance payments remained on the books.

Why SoftBank Losses Widened Beyond Ohio

The equipment charge was not the only drag. SoftBank recorded a ¥321.9 billion derivative loss on Intel prepaid forward contracts after Intel's share price rose. It also booked a ¥270.1 billion Intel valuation loss in the quarter, per the earnings presentation.

Its Vision Fund segment lost ¥81.6 billion before tax in the quarter, per the data sheet. Lower share prices at Arm Holdings, Intel and Coupang also weighed on results, Bloomberg reported via The Japan Times.

Borrowing costs climbed as well. Interest expense at the parent company rose ¥407.2 billion from a year earlier to ¥676.4 billion for the six months. Part of the rise came from writing off fees when SoftBank repaid bridge loans early, the financial report says.

SoftBank Data Center Investment and Financing Strain

SoftBank raised $56.5 billion in the quarter and fully repaid a $40 billion bridge loan six months early, its investor briefing shows. Reuters called the raise SoftBank's largest quarterly total on record, as published by AOL.

The company completed $30 billion of follow-on investments in OpenAI on October 1, 2026, bringing its total to $64.6 billion for about 13%, per the financial report. It also paid $3.1 billion for DigitalBridge, a digital infrastructure manager, on September 30.

Chief financial officer Yoshimitsu Goto said the company had rushed to secure power equipment and has decided to "conduct a thorough reassessment," Bloomberg reported via Business Standard. "There are many cases where you have to change strategy for what you thought would probably have been OK a year or two ago," he said, according to Reuters via AOL.

Markets have been watching. SoftBank shares are down more than 50% from a June record, and its credit default swaps reached their highest in years, Bloomberg reported via The Japan Times. Reuters said the shares jumped 14% on November 10, 2026, ahead of the results, per AOL.

Morabito Investment Group Analysis

SoftBank wrote off $2.9 billion of $9.5 billion in advance equipment payments, or about 30.5%, according to a Morabito Investment Group analysis of the SoftBank earnings presentation. The full ¥597.2 billion charge equals about 53.5% of the quarter's ¥1,115.3 billion net loss, though the charge is a pretax figure.

The result also missed the average analyst forecast of a ¥129 billion profit by about ¥1,244 billion, based on SoftBank's data sheet and the Bloomberg estimate. A year earlier, the same quarter produced ¥2,502.2 billion of net income.

What This Means for Data Center Investors and Lenders

Power is now the long lead item for large data center campuses. Sponsors that prepay for turbines and other equipment can secure a place in line, but they also take on losses when plans change.

For lenders and land investors, the lesson is to look closely at a sponsor's advance payments, cancellation terms and rebate rights. This follows ING's sale of about $500 million of data center loans, including debt tied to a Stargate campus, and wider spreads on Meta and Oracle data center bond deals.

Demand is not the question SoftBank raised. Its charge reflects procurement timing on a campus that still has a signed tenant. Investors tracking big tech data center capex plans for 2026 and infrastructure real estate should watch how this equipment risk is priced into project loans.

Frequently Asked Questions

Where is the SoftBank data center in Ohio?

SoftBank's results name the PORTS-Pike Technology Campus in Pike County, Ohio. The company lists it at 8.0 gigawatts of IT capacity, preparing for construction as of September 30, 2026, per its earnings presentation. SB Energy says it reuses the former Portsmouth Gaseous Diffusion Plant site, per its press release.

Why did SoftBank post a loss?

SoftBank lost ¥1,115.3 billion in the quarter, per its data sheet. The main drivers were the ¥597.2 billion equipment charge and Intel related losses, per the earnings presentation. Higher finance costs also weighed on results.

Is the SoftBank Ohio project still going ahead?

SoftBank's materials still list the campus as preparing for construction, with OpenAI under a 20-year lease. The company says it realigned equipment purchases to signed contracts and kept $6.6 billion of advance payments, per the presentation.

Key Takeaways

  • SoftBank lost ¥1,115.3 billion in its fiscal second quarter, largely because of a $3.7 billion power equipment charge.
  • The charge covers equipment for U.S. AI data centers, including the PORTS-Pike Technology Campus in Pike County, Ohio.
  • About 30.5% of SoftBank's $9.5 billion in advance equipment payments was written off, a Morabito Investment Group analysis finds.

Bottom Line

SoftBank's loss shows the cost of buying power equipment before projects are fully defined. The Ohio campus remains in SoftBank's plans, but $3.7 billion is gone. Data center investors and lenders should treat equipment prepayments as a real credit risk.

Image credit: American Public Power Association, via Unsplash.

Sources

Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.