SK hynix New York Investment: Up to $100B Marcy Chip Plan Under Review, Not Final
SK hynix's New York investment, a Solidigm chip plan for Marcy Nanocenter that could reach about $100 billion, is under review and not final, Reuters and the Seoul Economic Daily reported on November 3, 2026.
SK hynix told the Seoul Economic Daily that the plan "is under review and nothing has been finalized." Solidigm, its U.S. memory unit, told Reuters that no decision on any specific course of action has been made.
By the Numbers
- About $45 billion: the initial investment Solidigm plans for two NAND memory plants in Marcy, New York, according to two people cited by Reuters. SBS, citing Bloomberg, reported the same $45 billion figure on October 27, 2026, per SBS News.
- About $100 billion: where total investment could reach over time, according to both Reuters and the Seoul Economic Daily.
- 434 acres: the size of the Marcy Nanocenter campus, with another 127 acres available for development, according to Marcy Nanocenter.
- 400 megawatts: the redundant power service a dual 115 kV transmission line brings to the site, according to Marcy Nanocenter.
- 35%: the federal advanced manufacturing investment credit, which does not apply to plants that begin construction after December 31, 2026, under 26 U.S. Code Section 48D.
What Happened With the SK hynix New York Investment
Solidigm makes NAND flash, the memory used for data storage in data centers. NAND keeps data even when the power is off, as Reuters explained. Solidigm has no U.S. chip plant today.
The Seoul Economic Daily reported that SK hynix and Solidigm have effectively settled on Marcy Nanocenter in Oneida County. It said they are working out investment terms with state and local agencies. A senior industry official told the paper that the size, groundbreaking timing and spending plan depend on those talks.
Tim Fitzgerald, a senior vice president at Mohawk Valley EDGE, told the Seoul Economic Daily that the agency is in negotiations with Oneida County and New York State "to attract a major company" to the site. Mohawk Valley EDGE is the lead developer of the campus, according to Marcy Nanocenter.
Funding is the open question. Solidigm halted its review of a U.S. initial public offering in October 2026, according to Reuters and the Seoul Economic Daily. The Korean paper said direct funding from SK hynix and outside borrowing are under discussion instead.
Solidigm New York Fab and the Export License Snag
On November 3, 2026, Reuters reported that the plan had hit a snag, citing people familiar with the matter. According to those sources, U.S. approval of export licenses for American chipmaking equipment for SK hynix's plant in Dalian, China has been held up.
SK hynix argues that more output in Dalian would help fund its planned U.S. expansion, the sources told Reuters. The Commerce Department has not formally denied a license to fill empty clean space in Dalian, and negotiations are continuing, the report said.
Businesskorea, citing the Reuters report, wrote that the industry has raised the possibility of a smaller U.S. investment or another site if the issue drags on. Solidigm told Reuters it is exploring potential locations around the world.
Why Marcy Nanocenter Matters to Investors
Site readiness is the main reason this campus keeps drawing chipmakers. Marcy Nanocenter describes itself as permit ready, with a dedicated substation, two 24 inch water mains and sewer and fiber already in place.
The campus already hosts Wolfspeed's $1.2 billion silicon carbide fab, which the site says will bring more than 600 jobs, per Marcy Nanocenter. The balance of the site can support about 1 million additional square feet of cleanroom space, according to Mohawk Valley EDGE.
New York has also funded site work. Marcy Nanocenter received $14 million in FAST NY shovel ready funding in August 2023, according to Marcy Nanocenter.
Morabito Investment Group Analysis
The Marcy campus offers 561 total acres, according to a Morabito Investment Group analysis of Marcy Nanocenter figures. That is the 434 acre campus plus the 127 acres available for further development.
The reported investment would also dwarf what is on the campus now. About $100 billion is roughly 83 times Wolfspeed's $1.2 billion fab, according to a Morabito Investment Group analysis of Reuters and Marcy Nanocenter figures. Even the initial $45 billion is about 37.5 times larger.
These are ratios on reported, unconfirmed figures. They are not a company commitment.
A Second Memory Megaproject in Central New York
Micron said on January 7, 2026 that it would break ground on January 16, 2026 on its megafab in Onondaga County, according to a Micron press release. The $100 billion project is planned for up to four fabs.
We covered the wider factory pipeline in our post on the manufacturing construction slowdown and build-to-suit demand. Chip supply chain spending in New York also showed up in our November 1 industrial real estate deals roundup.
If Solidigm goes ahead, the region would host two large memory projects at once. That would likely draw suppliers, contractors and workers to the Utica and Syracuse areas over many years.
Implications for Investors, Owners and Developers
Fabs pull demand well beyond the fence line. Equipment suppliers, chemical and gas providers and maintenance firms often want flex and warehouse space near the plant. Read more on that asset class on our industrial real estate sector page.
Housing is the second effect. A large construction workforce, then plant staff, would add demand for rentals and new homes in Oneida County. Investors watching the region may track land prices, multifamily permits and rents near Utica.
The timing risk is real. Large chip projects often slip, shrink or move, and this one depends on financing and a federal license decision. The federal investment credit also ends for plants that start construction after December 31, 2026, under Section 48D.
What to Watch Next
- A formal SK hynix disclosure. The Seoul Economic Daily said SK hynix pledged on October 29, 2026 to disclose details once they are final or within one month.
- Any decision on the Dalian export licenses, which Reuters sources called central to the New York plans.
- State and local incentive approvals and any site preparation grants for Marcy Nanocenter.
Frequently Asked Questions
Is the SK hynix New York investment final?
No. SK hynix told the Seoul Economic Daily that the plan is under review and nothing has been finalized. Solidigm told Reuters that no decision on any specific course of action has been made.
Where would the Solidigm New York fab be built?
Reports point to Marcy Nanocenter in Marcy, Oneida County. Reuters said the plan is for two NAND plants in Marcy. The campus covers 434 acres on the SUNY Polytechnic Utica campus, according to Marcy Nanocenter.
What happened to the Solidigm IPO?
Solidigm halted its review of U.S. IPO options because of market conditions and share price trends, SK hynix said in an October 23, 2026 statement cited by Reuters. The Seoul Economic Daily said this leaves the company looking at other ways to fund the fab.
Key Takeaways
- SK hynix's Solidigm New York plan could reach about $100 billion over time, but SK hynix says it remains under review.
- Reuters sources say a held up U.S. export license for SK hynix's Dalian, China plant is complicating the New York plan.
- Marcy Nanocenter offers 561 total acres and 400 megawatts of power, with power, water and sewer already in place.
Bottom Line
The SK hynix New York investment would be one of the largest industrial projects in upstate New York if it happens. For now it is a reported plan, not a commitment. Investors should treat any land or housing thesis tied to it as early and conditional.
Image credit: Photo by Laura Ockel on Unsplash.
Sources
- Seoul Economic Daily, SK hynix Eyes New York Site for First U.S. NAND Plant, https://en.sedaily.com/finance/2026/11/03/sk-hynix-picks-new-york-site-for-first-us-nand-plant
- Reuters, SK Hynix's New York chip plans hit snag over US restrictions on China, sources say, https://www.reuters.com/world/china/sk-hynixs-new-york-chip-plans-hit-snag-over-us-restrictions-china-sources-say-2026-11-03/ (read via Yahoo Finance syndication: https://finance.yahoo.com/technology/articles/sk-hynixs-york-chip-plans-185003954.html)
- Businesskorea, SK hynix Investment in New York May Face Uncertainty, https://www.businesskorea.co.kr/news/articleView.html?idxno=280499
- SBS News, Bloomberg: SK Hynix Sub-Subsidiary Solidigm Pursuing $45 Billion NAND Plant in US, https://news.sbs.co.kr/english/article.do?news_id=N1008818117
- Marcy Nanocenter, Home, https://marcynanocenter.com/
- Marcy Nanocenter, Parcel 2, https://marcynanocenter.com/marcy-nanocenter-projects/parcel-2/
- Mohawk Valley EDGE, Available Site: Marcy Nano, https://www.mvedge.org/marcy-nanocenter/
- Legal Information Institute, 26 U.S. Code Section 48D, Advanced manufacturing investment credit, https://www.law.cornell.edu/uscode/text/26/48D
- Micron Technology, Micron Announces Groundbreaking for Historic New York Megafab, https://micron.gcs-web.com/node/49921
Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.
This article is for general information only. It is not legal, tax, financial, or investment advice, and it is not an offer to sell or a solicitation of an offer to buy any security. Talk to your own advisors before acting on anything in it. Views are current as of the publish date and may change without notice.