AT&T Headquarters Plano: Construction Set for Dec. 1 on $1.35B, 54-Acre Campus

Article details
Published:
October 20, 2026
Updated:
Read length:
7
 mins

Construction of the AT&T headquarters in Plano is set to start December 1, 2026, with completion targeted for March 31, 2029, according to Texas state filings first reported on October 14, 2026.

An affiliate of Dallas developer KDC registered 11 projects for the 54-acre AT&T headquarters Plano campus with the Texas Department of Licensing and Regulation (TDLR) on October 14, 2026, CRE Daily reported, citing The Dallas Morning News.

The current filings total an estimated $1.05 billion, while the full project has been reported at $1.35 billion, per Community Impact. A Morabito Investment Group analysis of the filed square footage puts the blended filed cost at about $210 per square foot.

By the Numbers

  • $1.05 billion: estimated cost of the 11 facilities in the current TDLR filings (Community Impact).
  • $1.35 billion: the minimum construction spend required by Plano's incentive agreement (The Dallas Morning News).
  • $201 million: filed estimate for Building 4, the largest office building at 679,000 square feet (CRE Daily).
  • 10,000: full-time on-site jobs AT&T must eventually employ under the city agreement (The Dallas Morning News).
  • $400 million: construction loan from JPMorgan Chase to KDC for the campus (CRE Daily).

AT&T Headquarters Plano: What the Construction Filings Show

The project owner named in the filings is KDC Legacy Eagle HQ Development One, LLC, CRE Daily reported. A KDC-affiliated company bought the site from affiliates of NexPoint Development. AT&T and KDC declined to discuss the filings with The Dallas Morning News.

The 11 facilities run along Legacy Drive and will be under construction through 2029, per Community Impact. The filed facilities break down as follows:

  • Building 1: 249,000 square feet of office, filed at $115.4 million.
  • Buildings 2 and 3: 225,000 square feet of office each.
  • Building 4: 679,000 square feet of office, filed at about $201 million.
  • Building 6: 229,000 square feet of office.
  • Building 7: 318,000 square feet with a fitness center, filed at $98.6 million.
  • Building 8: 215,700 square feet with the office lobby and a food hall.
  • Central utility plant: 32,000 square feet, filed at $75.8 million.
  • Garage A: 553,000 square feet. Garage B: nearly 1.1 million square feet. Garage C: nearly 1.18 million square feet.

Square footage comes from Community Impact, and the four cost figures come from CRE Daily. No filing exists for a Building 5, CRE Daily noted.

How the Reports Differ on Cost and Size

The published reports do not use identical totals for cost or building area. Connect CRE values the campus at $1.3 billion, with more than 2.3 million square feet of office and more than 2.5 million square feet of garages. Community Impact and The Dallas Morning News use $1.35 billion, the spending floor in the city agreement.

CRE Daily tallied the seven office buildings at roughly 2.2 million square feet. It described the three garages as about 2.3 million square feet combined. Adding the Community Impact garage figures gives about 2.83 million square feet, so readers should treat garage totals as approximate.

MIG Analysis: Filed Cost per Square Foot

According to a Morabito Investment Group analysis of the TDLR figures reported by Community Impact and CRE Daily, the 11 filed facilities total about 5.0 million square feet.

That count includes 2.14 million square feet in the seven office buildings, 32,000 square feet in the utility plant and about 2.83 million square feet of garages. Dividing the $1.05 billion filed estimate by that area gives about $210 per square foot.

The blended figure is relatively low because parking garages make up about 57% of the filed area, so the individual office filings run considerably higher. Building 4 works out to about $296 per square foot, Building 7 to about $310 and Building 1 to about $463.

The four disclosed line items total $490.8 million, or about 47% of the filed estimate, which leaves about $559.2 million for Buildings 2, 3, 6 and 8 and the three garages.

The $300 million gap between the filings and the $1.35 billion floor may cover costs not yet filed, such as site work, interiors or other items. The sources do not break that out.

Plano Incentive Terms for the New AT&T Headquarters

The Plano City Council approved a $20 million incentive package on February 23, 2026, per Community Impact. It is the largest the city has given a private employer, The Dallas Morning News reported.

Under the Chapter 380 agreement, a Texas tool that lets cities grant incentives for economic development, AT&T must spend at least $1.35 billion on construction. It must build at least 2 million square feet of office, amenity and retail space. It must also eventually employ 10,000 full-time workers on site and occupy the campus for 25 years.

In return, AT&T receives the $20 million in grants and a 65% rebate on property taxes on site improvements for 25 years starting in 2030. The rebate could run 10 more years at 25% if AT&T buys the site, per CRE Daily. The $20 million grant equals about 1.5% of the $1.35 billion spending floor, by MIG's calculation.

Why the AT&T Plano Headquarters Matters for Investors

AT&T announced in January 2026 that it would leave downtown Dallas for the former Electronic Data Systems (EDS) campus at 5400 Legacy Drive, per Community Impact. The campus will consolidate its Dallas-Fort Worth administrative space, including its three largest sites in Central Dallas, Plano and Irving.

Chief executive John Stankey called it "a corporate campus designed for collaboration, innovation and engagement," Dallas Innovates reported.

The move is a large example of a tenant choosing a new, purpose-built campus over existing towers.

That choice fits a wider pattern of corporate demand concentrating in new, amenity-rich space, a trend covered in our look at trophy office rents in the 2026 U.S. office market. Google's planned move of 2,500 workers to Chicago's Thompson Center is another large corporate relocation, covered in our report on the Thompson Center Google Chicago move.

For downtown Dallas owners, the exit creates a backfill question. AT&T's current home, the roughly 1 million square foot Whitacre Tower, has a lease that runs through the end of 2031, Bisnow reported, citing The Dallas Morning News.

AT&T occupies about 3 million square feet of office space in Dallas, more than any other private employer in the city, according to CoStar data cited by CRE Daily.

Implications for Build-to-Suit Owners, Lenders and Developers

Large corporate campuses are often structured as build-to-suit projects, where a developer builds to one tenant's specifications. Here, KDC is the developer and the filings list a KDC affiliate as owner. The incentive terms mention a possible site purchase by AT&T, which signals that final ownership could change.

Incentive conditions matter in underwriting, because a rebate tied to employment, spending and a 25-year occupancy commitment can shift a project's long-term property tax costs. Investors in comparable deals usually study who bears the financial risk if performance benchmarks are missed, and lenders also monitor these terms, as JPMorgan's $400 million construction loan shows.

Construction costs are another variable for a schedule running into 2029. Long timelines leave large owner-occupied projects exposed to cost changes, a theme in our coverage of the manufacturing construction pipeline and build-to-suit demand.

What to Watch

  • Whether construction begins on December 1, 2026, as filed. Demolition on the site was still underway as of October 19, 2026, per Connect CRE.
  • Partial occupancy. Stankey has said AT&T could partly occupy the campus in the second half of 2028, ahead of the March 2029 target.
  • Further filings that could close the gap between $1.05 billion and $1.35 billion.
  • Leasing plans for Whitacre Tower and AT&T's other Dallas space before 2031.

Frequently Asked Questions

Where will the new AT&T headquarters be located?

The new AT&T headquarters will sit on 54 acres at 5400 Legacy Drive in Plano, Texas, the former EDS campus, per Community Impact. The site lies along Legacy Drive and Parkwood Boulevard, per Connect CRE.

When will the AT&T Plano headquarters campus be finished?

State filings target completion by March 31, 2029, with construction starting December 1, 2026, per CRE Daily. AT&T has said partial occupancy could come in the second half of 2028.

What will the AT&T Plano headquarters tower look like?

The campus will include a 280-foot antenna tower, which Plano's planning and zoning commission approved on May 4, 2026, per Community Impact. The tower will display AT&T's logo and still needs FAA approval, Bisnow reported in May 2026.

Key Takeaways

  • Construction of the AT&T headquarters in Plano is filed to start December 1, 2026, and finish by March 31, 2029.
  • The 11 filed facilities total $1.05 billion, or about $210 per square foot, by a Morabito Investment Group analysis.
  • Plano's $20 million incentive requires at least $1.35 billion in spending, 10,000 on-site jobs and a 25-year stay.

Bottom Line

The AT&T campus is one of the largest corporate headquarters projects now headed into construction in the U.S. The filings give investors a rare look at the cost of a single-tenant campus, garage by garage. For downtown Dallas, the open question is how a 1 million square foot tower gets reused after 2031.

Image credit: Photo by Alex Reynolds on Unsplash.

Sources

Disclaimer: This article is for general information and education only. It is not investment, financial, legal, tax or accounting advice, and it is not an offer or solicitation to buy or sell any security or property. Morabito Investment Group does not guarantee that the information is complete, accurate or current. Figures, forecasts and opinions from third parties belong to their sources. All investments carry risk, including loss of principal, and past results do not guarantee future results. Do your own research and consult a licensed professional before making any investment, financing or other decision. You use this information at your own risk.